N84 Grid

Taunton Main Bsp

DNO substation.

Contracted here0.12 GWNot yet connected, as printed
Entries in the queue6entries with a printed MW
Earliest connection date25 Jan 2027Date printed in the register

The queue, in order

Order calculated by N84
First in queue121.6 MW across the first 6 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Taunton Main Bsp (solar)30 Sep 202525 Jan 20274.4 MW
Taunton Main Bsp (solar)25 Feb 20264 Mar 20277.3 MW
Taunton Main Bsp (bess)24 Nov 202121 May 202720 MW
Taunton Main Bsp (solar)17 Jan 202525 May 202720 MW
Taunton Main Bsp (bess)11 Mar 20224 Jun 202749.9 MW
Taunton Main Bsp (solar)7 Oct 202112 Jul 202720 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW100 MW200 MW2027: 122 MW2027122 MW
0 MW100 MW200 MW2027: 122 MW2027122 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
2027121.6 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Taunton Main Bsp (solar)4.4 MW0 MW25 Jan 2027not statedgate not printedAccepted to Connect
2Taunton Main Bsp (solar)7.3 MW4.4 MW4 Mar 2027not statedgate not printedAccepted to Connect
3Taunton Main Bsp (bess)20 MW11.7 MW21 May 2027not statedgate not printedAccepted to Connect
4Taunton Main Bsp (solar)20 MW31.7 MW25 May 2027not statedgate not printedAccepted to Connect
5Taunton Main Bsp (bess)49.9 MW51.7 MW4 Jun 2027not statedgate not printedAccepted to Connect
6Taunton Main Bsp (solar)20 MW101.6 MW12 Jul 2027not statedgate not printedAccepted to Connect

Receipt: MW and dates as printed in the NGED Embedded Capacity Register, file dated 14 Aug 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
20276121.6 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Taunton Main Bsp (battery, 49.9 MW)Battery storage49.9 MW4 Jun 2027Accepted to Connect
Taunton Main Bsp (battery, 30 MW)Battery storage30 MWnot statedConnected
Taunton Main Bsp (gas, 20.43 MW)Gas20.43 MWnot statedConnected
Taunton Main Bsp (solar, 20 MW)Solar20 MW12 Jul 2027Accepted to Connect
Taunton Main Bsp (solar, 20 MW)Solar20 MW25 May 2027Accepted to Connect
Taunton Main Bsp (battery, 20 MW)Battery storage20 MW21 May 2027Accepted to Connect
Taunton Main Bsp (solar, 7.3 MW)Solar7.3 MW4 Mar 2027Accepted to Connect
Taunton Main Bsp (solar, 7.13 MW)Solar7.13 MWnot statedConnected
Taunton Main Bsp (solar, 6.81 MW)Solar6.81 MWnot statedConnected
Taunton Main Bsp (solar, 4.75 MW)Solar4.75 MWnot statedConnected
Taunton Main Bsp (solar, 4.44 MW)Solar4.44 MWnot statedConnected
Taunton Main Bsp (solar, 4.4 MW)Solar4.4 MW25 Jan 2027Accepted to Connect
Taunton Main Bsp (solar, 4.36 MW)Solar4.36 MWnot statedConnected
Taunton Main Bsp (solar, 3.88 MW)Solar3.88 MWnot statedConnected
Taunton Main Bsp (solar, 3.88 MW)Solar3.88 MWnot statedConnected
Taunton Main Bsp (solar, 3.75 MW)Solar3.75 MWnot statedConnected
Taunton Main Bsp (solar, 3.71 MW)Solar3.71 MWnot statedConnected

Supported by NGED Open Data