N84 Grid

Tividale 132/11Kv

DNO substation.

Contracted here0.00 GWNot yet connected, as printed
Entries in the queue4entries with a printed MW
Earliest connection date11 Nov 2026Date printed in the register

The queue, in order

Order calculated by N84
First in queue0.74 MW across the first 4 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Tividale 132/11Kv (solar)2 Dec 202211 Nov 20260.06 MW
Tividale 132/11Kv (solar)16 Jul 20244 Feb 20270.12 MW
Tividale 132/11Kv (solar)29 May 20241 Mar 20270.5 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW0 MW1 MW2026: 0 MW2027: 1 MW202620271 MW
0 MW0 MW1 MW2026: 0 MW2027: 1 MW202620271 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
20260.06 MW
20270.68 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Tividale 132/11Kv (solar)0.06 MW0 MW11 Nov 2026not statedgate not printedAccepted to Connect
2Tividale 132/11Kv (solar)0.12 MW0.06 MW4 Feb 2027not statedgate not printedAccepted to Connect
3Tividale 132/11Kv (solar)0.5 MW0.18 MW1 Mar 2027not statedgate not printedAccepted to Connect
4Tividale 132/11Kv (solar)0.06 MW0.68 MWnot statednot statedgate not printedAccepted to Connect

Receipt: MW and dates as printed in the NGED Embedded Capacity Register, file dated 14 Aug 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
202610.06 MW
202720.62 MW
not stated10.06 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Tividale 132/11Kv (solar, 0.5 MW)Solar0.5 MW1 Mar 2027Accepted to Connect
Tividale 132/11Kv (solar, 0.36 MW)Solar0.36 MWnot statedConnected
Tividale 132/11Kv (solar, 0.12 MW)Solar0.12 MW4 Feb 2027Accepted to Connect
Tividale 132/11Kv (solar, 0.09 MW)Solar0.09 MWnot statedConnected
Tividale 132/11Kv (solar, 0.06 MW)Solar0.06 MW11 Nov 2026Accepted to Connect
Tividale 132/11Kv (solar, 0.03 MW)Solar0.03 MWnot statedAccepted to Connect

Supported by NGED Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.