N84 Grid

Totnes Bsp

DNO substation.

Contracted here0.11 GWNot yet connected, as printed
Entries in the queue3entries with a printed MW
Earliest connection date30 Nov 2026Date printed in the register

The queue, in order

Order calculated by N84
First in queue106 MW across the first 3 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Totnes (solar)20 Nov 202530 Nov 20262 MW
Totnes Bsp (solar)8 Jan 20267 Jun 20275 MW
Totnes Bsp (bess)4 Mar 202414 Jun 202799 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW100 MW200 MW2026: 2 MW2027: 106 MW20262027106 MW
0 MW100 MW200 MW2026: 2 MW2027: 106 MW20262027106 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
20262 MW
2027106 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Totnes (solar)2 MW0 MW30 Nov 2026not statedgate not printedAccepted to Connect
2Totnes Bsp (solar)5 MW2 MW7 Jun 2027not statedgate not printedAccepted to Connect
3Totnes Bsp (bess)99 MW7 MW14 Jun 2027not statedgate not printedAccepted to Connect

Receipt: MW and dates as printed in the NGED Embedded Capacity Register, file dated 14 Aug 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
202612 MW
20272104 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Totnes Bsp (battery, 99 MW)Battery storage99 MW14 Jun 2027Accepted to Connect
Totnes Bsp (solar, 8.07 MW)Solar8.07 MWnot statedConnected
Totnes Bsp (solar, 7.27 MW)Solar7.27 MWnot statedConnected
Totnes Bsp (solar, 5 MW)Solar5 MW7 Jun 2027Accepted to Connect
Totnes Bsp (solar, 4.81 MW)Solar4.81 MWnot statedConnected
Totnes Bsp (solar, 4.75 MW)Solar4.75 MWnot statedConnected
Totnes Bsp (solar, 4.75 MW)Solar4.75 MWnot statedConnected
Totnes Bsp (solar, 4.7 MW)Solar4.7 MWnot statedConnected
Totnes Bsp (solar, 3.88 MW)Solar3.88 MWnot statedConnected
Totnes Bsp (solar, 0.47 MW)Solar0.48 MWnot statedConnected
Totnes Bsp (hybrid, 0.28 MW)Hybrid0.28 MWnot statedConnected
Totnes Bsp (hydro, 0.14 MW)Hydro and pumped storage0.14 MWnot statedConnected
Totnes Bsp (hydro, 0.14 MW)Hydro and pumped storage0.14 MWnot statedConnected
Totnes Bsp (solar, 0.1 MW)Solar0.1 MW30 Nov 2026Accepted to Connect

Supported by NGED Open Data