The queue, in order
Dates in the queue
From the earliest date we hold to the connection date printed, in queue order
- Uskmouth (hybrid)
11 Jul 2025 to 2 Dec 2026 (gate not printed) - Uskmouth (wind on)
12 Mar 2025 to 29 Dec 2026 (gate not printed) - Uskmouth (solar)
24 Jul 2018 to 19 Jan 2027 (gate not printed) - Uskmouth (solar)
7 Jun 2021 to 18 Mar 2027 (gate not printed) - Uskmouth (hybrid)
3 Apr 2025 to 29 Jul 2027 (gate not printed) - Uskmouth (wind on)
24 Mar 2020 to 23 Jan 2030 (gate not printed)
Table view
| Project | From | Connection date | MW |
|---|---|---|---|
| Uskmouth (hybrid) | 11 Jul 2025 | 2 Dec 2026 | 74 MW |
| Uskmouth (wind on) | 12 Mar 2025 | 29 Dec 2026 | 48 MW |
| Uskmouth (solar) | 24 Jul 2018 | 19 Jan 2027 | 49.99 MW |
| Uskmouth (solar) | 7 Jun 2021 | 18 Mar 2027 | 199.88 MW |
| Uskmouth (hybrid) | 3 Apr 2025 | 29 Jul 2027 | 195 MW |
| Uskmouth (wind on) | 24 Mar 2020 | 23 Jan 2030 | 18.6 MW |
Contracted MW as dates arrive
Running total by connection year, years to scale
Table view
| Year | Cumulative MW |
|---|---|
| 2026 | 122 MW |
| 2027 | 566.87 MW |
| 2030 | 585.47 MW |
Queue
| Placecalculated by N84 | Project | MW (as published) | MW ahead (N84 order) | Connection date | Gate | Order group | Status (as printed) |
|---|---|---|---|---|---|---|---|
| 1 | Uskmouth (hybrid) | 74 MW | 0 MW | 2 Dec 2026 | not stated | gate not printed | Accepted to Connect |
| 2 | Uskmouth (wind on) | 48 MW | 74 MW | 29 Dec 2026 | not stated | gate not printed | Accepted to Connect |
| 3 | Uskmouth (solar) | 49.99 MW | 122 MW | 19 Jan 2027 | not stated | gate not printed | Accepted to Connect |
| 4 | Uskmouth (solar) | 199.88 MW | 171.99 MW | 18 Mar 2027 | not stated | gate not printed | Accepted to Connect |
| 5 | Uskmouth (hybrid) | 195 MW | 371.87 MW | 29 Jul 2027 | not stated | gate not printed | Accepted to Connect |
| 6 | Uskmouth (wind on) | 18.6 MW | 566.87 MW | 23 Jan 2030 | not stated | gate not printed | Accepted to Connect |
Receipt: MW and dates as printed in the NGED Embedded Capacity Register, file dated 14 Aug 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order
| Year (MW effective from) | Projects | MW |
|---|---|---|
| 2026 | 2 | 122 MW |
| 2027 | 3 | 444.87 MW |
| 2030 | 1 | 18.6 MW |
Projects recorded at this site
| Project (as published) | Technology | MW | Connection date | Status (as printed) |
|---|---|---|---|---|
| Uskmouth (hybrid, 130 MW) | Hybrid | 130 MW | 29 Jul 2027 | Accepted to Connect |
| Uskmouth (solar, 99.94 MW) | Solar | 99.94 MW | 18 Mar 2027 | Accepted to Connect |
| Uskmouth (hybrid, 74 MW) | Hybrid | 74 MW | 2 Dec 2026 | Accepted to Connect |
| Uskmouth (solar, 49.99 MW) | Solar | 49.99 MW | 19 Jan 2027 | Accepted to Connect |
| Uskmouth (onshore wind, 48 MW) | Onshore wind | 48 MW | 29 Dec 2026 | Accepted to Connect |
| Uskmouth (solar, 47.5 MW) | Solar | 47.5 MW | not stated | Connected |
| Uskmouth (onshore wind, 18.6 MW) | Onshore wind | 18.6 MW | 23 Jan 2030 | Accepted to Connect |