N84 Grid

Walpole 132Kv S Stn

DNO substation.

Contracted here0.32 GWNot yet connected, as printed
Entries in the queue5entries with a printed MW
Earliest connection date16 Feb 2027Date printed in the register

The queue, in order

Order calculated by N84
First in queue321.6 MW across the first 5 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Walpole 132Kv S Stn (solar)3 Oct 202316 Feb 202742 MW
Walpole 132Kv S Stn (solar)18 Jun 20218 Mar 202749.9 MW
Walpole 132Kv S Stn (solar)3 Aug 202117 Mar 202749.9 MW
Walpole 132Kv S Stn (thermal)27 Mar 202616 Sep 202780 MW
Walpole 132Kv S Stn (hybrid)3 May 202212 Nov 202799.8 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW200 MW400 MW2027: 322 MW2027322 MW
0 MW200 MW400 MW2027: 322 MW2027322 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
2027321.6 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Walpole 132Kv S Stn (solar)42 MW0 MW16 Feb 2027not statedgate not printedAccepted to Connect
2Walpole 132Kv S Stn (solar)49.9 MW42 MW8 Mar 2027not statedgate not printedAccepted to Connect
3Walpole 132Kv S Stn (solar)49.9 MW91.9 MW17 Mar 2027not statedgate not printedAccepted to Connect
4Walpole 132Kv S Stn (thermal)80 MW141.8 MW16 Sep 2027not statedgate not printedAccepted to Connect
5Walpole 132Kv S Stn (hybrid)99.8 MW221.8 MW12 Nov 2027not statedgate not printedAccepted to Connect

Receipt: MW and dates as printed in the NGED Embedded Capacity Register, file dated 14 Aug 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
20275321.6 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Walpole 132Kv S Stn (thermal, 80 MW)Thermal80 MW16 Sep 2027Accepted to Connect
Walpole 132Kv S Stn (solar, 49.9 MW)Solar49.9 MW8 Mar 2027Accepted to Connect
Walpole 132Kv S Stn (hybrid, 49.9 MW)Hybrid49.9 MW12 Nov 2027Accepted to Connect
Walpole 132Kv S Stn (solar, 42 MW)Solar42 MW16 Feb 2027Accepted to Connect
Walpole 132Kv S Stn (solar, 39.9 MW)Solar39.9 MW17 Mar 2027Accepted to Connect

Supported by NGED Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.