Weston Bsp 132Kv

DNO substation.

Contracted here0.32 GWNot yet connected, as printed
Entries in the queue6entries with a printed MW
Earliest connection date8 Aug 2026Already passed, not yet connected

The queue, in order

Order calculated by N84
First in queue316.81 MW across the first 6 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Weston Bsp 132Kv (hybrid)31 Jan 20238 Aug 202699.8 MW
Weston Bsp 132Kv (solar)24 Aug 202222 Dec 20263.52 MW
Weston Bsp 132Kv (solar)19 Apr 202314 Jun 202749.9 MW
Weston Bsp 132Kv (solar)12 Jan 202329 Jun 202749.9 MW
Weston Bsp 132Kv (solar)31 Aug 202131 Aug 202713.69 MW
Weston Bsp 132Kv (bess)15 Jul 20221 Dec 2027100 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW200 MW400 MW2026: 103 MW2027: 317 MW20262027317 MW
0 MW200 MW400 MW2026: 103 MW2027: 317 MW20262027317 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
2026103.32 MW
2027316.81 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Weston Bsp 132Kv (hybrid)99.8 MW0 MW8 Aug 2026not statedgate not printedAccepted to Connect
2Weston Bsp 132Kv (solar)3.52 MW99.8 MW22 Dec 2026not statedgate not printedAccepted to Connect
3Weston Bsp 132Kv (solar)49.9 MW103.32 MW14 Jun 2027not statedgate not printedAccepted to Connect
4Weston Bsp 132Kv (solar)49.9 MW153.22 MW29 Jun 2027not statedgate not printedAccepted to Connect
5Weston Bsp 132Kv (solar)13.69 MW203.12 MW31 Aug 2027not statedgate not printedAccepted to Connect
6Weston Bsp 132Kv (bess)100 MW216.81 MW1 Dec 2027not statedgate not printedAccepted to Connect

Receipt: MW and dates as printed in the NGED Embedded Capacity Register, file dated 14 Aug 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
20262103.32 MW
20274213.49 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Weston Bsp 132Kv (battery, 100 MW)Battery storage100 MW1 Dec 2027Accepted to Connect
Weston Bsp 132Kv (solar, 49.9 MW)Solar49.9 MW14 Jun 2027Accepted to Connect
Weston Bsp 132Kv (solar, 49.9 MW)Solar49.9 MW29 Jun 2027Accepted to Connect
Weston Bsp 132Kv (hybrid, 49.9 MW)Hybrid49.9 MW8 Aug 2026Accepted to Connect
Weston Bsp 132Kv (solar, 13.69 MW)Solar13.69 MW31 Aug 2027Accepted to Connect
Weston Bsp 132Kv (solar, 3.52 MW)Solar3.52 MW22 Dec 2026Accepted to Connect
Weston Bsp 132Kv (solar, 3.36 MW)Solar3.36 MWnot statedConnected