Ystradgynlais Grid

DNO substation.

Contracted here0.04 GWNot yet connected, as printed
Entries in the queue4entries with a printed MW
Earliest connection date30 Aug 2026Already passed, not yet connected

The queue, in order

Order calculated by N84
First in queue40.33 MW across the first 4 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Ystradgynlais Grid (solar)14 Feb 201830 Aug 20264.7 MW
Ystradgynlais Grid (hybrid)10 Jan 202530 Nov 20261.83 MW
Ystradgynlais Grid (wind on)7 May 20261 Jul 202818.8 MW
Ystradgynlais Grid (solar)28 Mar 202331 Dec 202815 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW25 MW50 MW2026: 7 MW2028: 40 MW20262027202840 MW
0 MW25 MW50 MW2026: 7 MW2028: 40 MW20262027202840 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
20266.53 MW
202840.33 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Ystradgynlais Grid (solar)4.7 MW0 MW30 Aug 2026not statedgate not printedAccepted to Connect
2Ystradgynlais Grid (hybrid)1.83 MW4.7 MW30 Nov 2026not statedgate not printedAccepted to Connect
3Ystradgynlais Grid (wind on)18.8 MW6.53 MW1 Jul 2028not statedgate not printedAccepted to Connect
4Ystradgynlais Grid (solar)15 MW25.33 MW31 Dec 2028not statedgate not printedAccepted to Connect

Receipt: MW and dates as printed in the NGED Embedded Capacity Register, file dated 14 Aug 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
202626.53 MW
2028233.8 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Ystradgynlais Grid (onshore wind, 18.8 MW)Onshore wind18.8 MW1 Jul 2028Accepted to Connect
Ystradgynlais Grid (solar, 15 MW)Solar15 MW31 Dec 2028Accepted to Connect
Ystradgynlais Grid (hybrid, 5 MW)Hybrid5 MWnot statedConnected
Ystradgynlais Grid (solar, 4.7 MW)Solar4.7 MW30 Aug 2026Accepted to Connect
Ystradgynlais Grid (onshore wind, 4.46 MW)Onshore wind4.47 MWnot statedConnected
Ystradgynlais Grid (other, 4.18 MW)Other4.18 MWnot statedConnected
Ystradgynlais Grid (hybrid)Hybrid0 MW30 Nov 2026Accepted to Connect