N84 Grid

AMESBURY

DNO substation.

Contracted here0.04 GWNot yet connected, as printed
Entries in the queue2entries with a printed MW
Earliest connection date17 Dec 2025Already passed, not yet connected

The queue, in order

Order calculated by N84
First in queue40.22 MW across the first 2 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

  • AMESBURY (solar)17 Dec 2024 to 17 Dec 2025, date already passed (gate not printed)
  • AMESBURY (solar)21 Aug 2019 to 22 Dec 2027 (gate not printed)
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
AMESBURY (solar)17 Dec 202417 Dec 20250.22 MW
AMESBURY (solar)21 Aug 201922 Dec 202740 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW25 MW50 MW2025: 0 MW2027: 40 MW20252026202740 MW
0 MW25 MW50 MW2025: 0 MW2027: 40 MW20252026202740 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
20250.22 MW
202740.22 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1AMESBURY (solar)0.22 MW0 MW17 Dec 2025not statedgate not printedAccepted to Connect
2AMESBURY (solar)40 MW0.22 MW22 Dec 2027not statedgate not printedAccepted to Connect

Receipt: MW and dates as printed in the SSEN Embedded Capacity Register, file dated 1 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
202510.22 MW
2027140 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
AMESBURY (solar, 40 MW)Solar40 MW22 Dec 2027Accepted to Connect
AMESBURY (solar, 0.22 MW)Solar0.22 MW17 Dec 2025Accepted to Connect

Contains data from Scottish and Southern Electricity Networks, licensed under CC BY 4.0.