N84 Grid

ARBROATH GRID

DNO substation.

Contracted here0.34 GWNot yet connected, as printed
Entries in the queue7entries with a printed MW
Earliest connection date31 Dec 2026Date printed in the register

The queue, in order

Order calculated by N84
First in queue291.37 MW across the first 6 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
ARBROATH GRID (solar)16 Dec 202431 Dec 20268.8 MW
ARBROATH GRID (bess)8 Aug 202230 Jun 203252.68 MW
ARBROATH GRID (solar)3 Apr 202330 Jun 203272.42 MW
ARBROATH (hybrid)6 Jul 202330 Jun 203250 MW
ARBROATH (bess)6 Sep 202331 Oct 203250 MW
ARBROATH GRID (solar)2 Jul 202431 Oct 203257.47 MW
ARBROATH GRID (bess)2 Sep 202430 Nov 203249.9 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW200 MW400 MW2026: 9 MW2032: 341 MW2026202720282029203020312032341 MW
0 MW200 MW400 MW2026: 9 MW2032: 341 MW2026202820302032341 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
20268.8 MW
2032341.27 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1ARBROATH GRID (solar)8.8 MW0 MW31 Dec 2026not statedgate not printedAccepted to Connect
2ARBROATH GRID (bess)52.68 MW8.8 MW30 Jun 2032not statedgate not printedAccepted to Connect
3ARBROATH GRID (solar)72.42 MW61.48 MW30 Jun 2032not statedgate not printedAccepted to Connect
4ARBROATH (hybrid)50 MW133.9 MW30 Jun 2032not statedgate not printedAccepted to Connect
5ARBROATH (bess)50 MW183.9 MW31 Oct 2032not statedgate not printedAccepted to Connect
6ARBROATH GRID (solar)57.47 MW233.9 MW31 Oct 2032not statedgate not printedAccepted to Connect
7ARBROATH GRID (bess)49.9 MW291.37 MW30 Nov 2032not statedgate not printedAccepted to Connect

Receipt: MW and dates as printed in the SSEN Embedded Capacity Register, file dated 1 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
202618.8 MW
20326332.47 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
ARBROATH GRID (battery, 52.68 MW)Battery storage50 MW30 Jun 2032Accepted to Connect
ARBROATH GRID (hybrid, 50 MW)Hybrid50 MW30 Jun 2032Accepted to Connect
ARBROATH GRID (battery, 49.9 MW)Battery storage49.9 MW30 Nov 2032Accepted to Connect
ARBROATH GRID (solar, 72.42 MW)Solar49.9 MW30 Jun 2032Accepted to Connect
ARBROATH GRID (battery, 50 MW)Battery storage49.9 MW31 Oct 2032Accepted to Connect
ARBROATH GRID (solar, 57.47 MW)Solar49.9 MW31 Oct 2032Accepted to Connect
ARBROATH GRID (solar, 9.03 MW)Solar9.03 MWnot statedConnected
ARBROATH GRID (solar, 8.8 MW)Solar8 MW31 Dec 2026Accepted to Connect
ARBROATH GRID (solar, 4.75 MW)Solar4.75 MWnot statedConnected
ARBROATH GRID (solar, 4.75 MW)Solar4.75 MWnot statedConnected
ARBROATH GRID (solar, 4.51 MW)Solar4.51 MWnot statedConnected
ARBROATH GRID (other, 0.47 MW)Other0.48 MWnot statedConnected
ARBROATH GRID (other, 0.25 MW)Other0.17 MWnot statedConnected
ARBROATH GRID (solar, 24.84 MW)Solar0 MWnot statedAccepted to Connect
ARBROATH GRID (solar, 24.84 MW)Solar0 MWnot statedAccepted to Connect
ARBROATH GRID (battery, 20 MW)Battery storage0 MW31 Oct 2032Accepted to Connect
ARBROATH GRID (battery, 20 MW)Battery storage0 MWnot statedAccepted to Connect
ARBROATH GRID (battery, 24.75 MW)Battery storage0 MWnot statedAccepted to Connect
ARBROATH GRID (battery, 49.5 MW)Battery storage0 MWnot statedAccepted to Connect
ARBROATH GRID (solar, 72.42 MW)Solar0 MWnot statedAccepted to Connect
ARBROATH GRID (battery, 54.45 MW)Battery storage0 MWnot statedAccepted to Connect
ARBROATH GRID (other, 37.67 MW)Other0 MWnot statedAccepted to Connect
ARBROATH GRID (solar, 3.5 MW)Solar0 MWnot statedAccepted to Connect
ARBROATH GRID (solar, 0.16 MW)Solar0 MWnot statedAccepted to Connect
ARBROATH GRID (solar, 37.5 MW)Solar0 MWnot statedAccepted to Connect
ARBROATH GRID (hybrid, 60 MW)Hybrid0 MW31 Oct 2033Accepted to Connect

Contains data from Scottish and Southern Electricity Networks, licensed under CC BY 4.0.

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.