N84 Grid

ARNCOTT

DNO substation.

Contracted here0.00 GWNot yet connected, as printed
Entries in the queue6entries with a printed MW
Earliest connection date4 Jun 2025Already passed, not yet connected

The queue, in order

Order calculated by N84
First in queue4.56 MW across the first 6 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
ARNCOTT (solar)10 Nov 20214 Jun 20250.5 MW
ARNCOTT (solar)25 Jul 20258 Aug 20251.9 MW
ARNCOTT (solar)17 Nov 202517 Nov 20260.45 MW
ARNCOTT (solar)18 May 202618 May 20270.66 MW
ARNCOTT (solar)1 Sep 20261 Sep 20270.1 MW
ARNCOTT (solar)30 Jun 202531 Dec 20310.95 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW3 MW5 MW2025: 2 MW2026: 3 MW2027: 4 MW2031: 5 MW20252026202720282029203020315 MW
0 MW3 MW5 MW2025: 2 MW2026: 3 MW2027: 4 MW2031: 5 MW20252027202920315 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
20252.4 MW
20262.85 MW
20273.61 MW
20314.56 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1ARNCOTT (solar)0.5 MW0 MW4 Jun 2025not statedgate not printedAccepted to Connect
2ARNCOTT (solar)1.9 MW0.5 MW8 Aug 2025not statedgate not printedAccepted to Connect
3ARNCOTT (solar)0.45 MW2.4 MW17 Nov 2026not statedgate not printedAccepted to Connect
4ARNCOTT (solar)0.66 MW2.85 MW18 May 2027not statedgate not printedAccepted to Connect
5ARNCOTT (solar)0.1 MW3.51 MW1 Sep 2027not statedgate not printedAccepted to Connect
6ARNCOTT (solar)0.95 MW3.61 MW31 Dec 2031not statedgate not printedAccepted to Connect

Receipt: MW and dates as printed in the SSEN Embedded Capacity Register, file dated 1 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
202522.4 MW
202610.45 MW
202720.76 MW
203110.95 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
ARNCOTT (solar, 1.9 MW)Solar1.9 MW8 Aug 2025Accepted to Connect
ARNCOTT (solar, 0.95 MW)Solar0.95 MW31 Dec 2031Accepted to Connect
ARNCOTT (solar, 0.66 MW)Solar0.5 MW18 May 2027Accepted to Connect
ARNCOTT (solar, 0.5 MW)Solar0.5 MW4 Jun 2025Accepted to Connect
ARNCOTT (solar, 0.45 MW)Solar0.45 MW17 Nov 2026Accepted to Connect
ARNCOTT (other, 0.38 MW)Other0.38 MWnot statedConnected
ARNCOTT (solar, 0.1 MW)Solar0.1 MW1 Sep 2027Accepted to Connect
ARNCOTT (solar, 0.1 MW)Solar0 MWnot statedAccepted to Connect

Contains data from Scottish and Southern Electricity Networks, licensed under CC BY 4.0.

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.