ASHTON PARK

DNO substation.

Contracted here0.03 GWNot yet connected, as printed
Entries in the queue2entries with a printed MW
Earliest connection date29 Jan 2026Already passed, not yet connected

The queue, in order

Order calculated by N84
First in queue26.73 MW across the first 2 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

  • ASHTON PARK (solar)29 Jan 2025 to 29 Jan 2026, date already passed (gate not printed)
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
ASHTON PARK (solar)29 Jan 202529 Jan 202626.6 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW20 MW40 MW2026: 27 MW202627 MW
0 MW20 MW40 MW2026: 27 MW202627 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
202626.6 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1ASHTON PARK (solar)26.6 MW0 MW29 Jan 2026not statedgate not printedAccepted to Connect
2ASHTON PARK (solar)0.13 MW26.6 MWnot statednot statedgate not printedAccepted to Connect

Receipt: MW and dates as printed in the SSEN Embedded Capacity Register, file dated 1 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
2026126.6 MW
not stated10.13 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
ASHTON PARK (solar, 26.6 MW)Solar25 MW29 Jan 2026Accepted to Connect
ASHTON PARK (gas, 3.8 MW)Gas3.8 MWnot statedConnected
ASHTON PARK (solar, 0.13 MW)Solar0.13 MWnot statedAccepted to Connect
ASHTON PARK (solar, 0.08 MW)Solar0 MW2 May 2026Accepted to Connect
ASHTON PARK (solar, 8 MW)Solar0 MWnot statedAccepted to Connect

Contains data from Scottish and Southern Electricity Networks, licensed under CC BY 4.0.