AXMINSTER

DNO substation.

Contracted here0.12 GWNot yet connected, as printed
Entries in the queue3entries with a printed MW
Earliest connection date30 Oct 2026Date printed in the register

The queue, in order

Order calculated by N84
First in queue120.1 MW across the first 3 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
AXMINSTER (solar)25 Jan 202230 Oct 202635 MW
AXMINSTER (solar)29 Feb 20245 Mar 202932.6 MW
AXMINSTER (bess)5 Dec 20223 Jun 203852.5 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW100 MW200 MW2026: 35 MW2029: 68 MW2038: 120 MW2026202820302032203420362038120 MW
0 MW100 MW200 MW2026: 35 MW2029: 68 MW2038: 120 MW2026203020342038120 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
202635 MW
202967.6 MW
2038120.1 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1AXMINSTER (solar)35 MW0 MW30 Oct 2026not statedgate not printedAccepted to Connect
2AXMINSTER (solar)32.6 MW35 MW5 Mar 2029not statedgate not printedAccepted to Connect
3AXMINSTER (bess)52.5 MW67.6 MW3 Jun 2038not statedgate not printedAccepted to Connect

Receipt: MW and dates as printed in the SSEN Embedded Capacity Register, file dated 1 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
2026135 MW
2029132.6 MW
2038152.5 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
AXMINSTER (battery, 52.5 MW)Battery storage49.9 MW3 Jun 2038Accepted to Connect
AXMINSTER (solar, 35 MW)Solar35 MW30 Oct 2026Accepted to Connect
AXMINSTER (solar, 32.6 MW)Solar30 MW5 Mar 2029Accepted to Connect
AXMINSTER (other, 0.43 MW)Other0.43 MWnot statedConnected
AXMINSTER (other, 0.1 MW)Other0.1 MWnot statedConnected
AXMINSTER (hybrid, 99.35 MW)Hybrid0 MW31 May 2030Accepted to Connect
AXMINSTER (battery, 52.5 MW)Battery storage0 MWnot statedAccepted to Connect
AXMINSTER (solar, 32.6 MW)Solar0 MWnot statedAccepted to Connect

Contains data from Scottish and Southern Electricity Networks, licensed under CC BY 4.0.