BARTON STACEY

DNO substation.

Contracted here0.02 GWNot yet connected, as printed
Entries in the queue2entries with a printed MW
Earliest connection date15 Jul 2028Date printed in the register

The queue, in order

Order calculated by N84
First in queue17.2 MW across the first 2 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
BARTON STACEY (solar)8 Jul 202415 Jul 20287.2 MW
BARTON STACEY (hybrid)31 Mar 202531 Dec 203710 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW10 MW20 MW2028: 7 MW2037: 17 MW20282030203220342036203717 MW
0 MW10 MW20 MW2028: 7 MW2037: 17 MW202820312034203717 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
20287.2 MW
203717.2 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1BARTON STACEY (solar)7.2 MW0 MW15 Jul 2028not statedgate not printedAccepted to Connect
2BARTON STACEY (hybrid)10 MW7.2 MW31 Dec 2037not statedgate not printedAccepted to Connect

Receipt: MW and dates as printed in the SSEN Embedded Capacity Register, file dated 1 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
202817.2 MW
2037110 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
BARTON STACEY (hybrid, 10 MW)Hybrid10 MW31 Dec 2037Accepted to Connect
BARTON STACEY (solar, 7.2 MW)Solar7.2 MW15 Jul 2028Accepted to Connect
BARTON STACEY (other, 0.06 MW)Other0.06 MWnot statedConnected
BARTON STACEY (other, 0.13 MW)Other0.05 MWnot statedConnected

Contains data from Scottish and Southern Electricity Networks, licensed under CC BY 4.0.

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.