BRACO WEST GRID

DNO substation.

Contracted here0.30 GWNot yet connected, as printed
Entries in the queue6entries with a printed MW
Earliest connection date30 Jun 2025Already passed, not yet connected

The queue, in order

Order calculated by N84
First in queue295.6 MW across the first 6 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
BRACO WEST GRID (solar)31 Jan 202430 Jun 202515.9 MW
BRACO WEST GRID (bess)28 Aug 20207 Jul 202649.9 MW
BRACO WEST GRID (bess)1 Nov 202131 Dec 202649.9 MW
BRACO WEST GRID (solar)16 Jul 202430 Aug 20279.9 MW
BRACO WEST GRID (wind on)21 Dec 202331 Oct 2035110 MW
BRACO WEST GRID (wind on)8 Dec 202531 May 203660 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW200 MW400 MW2025: 16 MW2026: 116 MW2027: 126 MW2035: 236 MW2036: 296 MW202520272029203120332036296 MW
0 MW200 MW400 MW2025: 16 MW2026: 116 MW2027: 126 MW2035: 236 MW2036: 296 MW20252028203120342036296 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
202515.9 MW
2026115.7 MW
2027125.6 MW
2035235.6 MW
2036295.6 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1BRACO WEST GRID (solar)15.9 MW0 MW30 Jun 2025not statedgate not printedAccepted to Connect
2BRACO WEST GRID (bess)49.9 MW15.9 MW7 Jul 2026not statedgate not printedAccepted to Connect
3BRACO WEST GRID (bess)49.9 MW65.8 MW31 Dec 2026not statedgate not printedAccepted to Connect
4BRACO WEST GRID (solar)9.9 MW115.7 MW30 Aug 2027not statedgate not printedAccepted to Connect
5BRACO WEST GRID (wind on)110 MW125.6 MW31 Oct 2035not statedgate not printedAccepted to Connect
6BRACO WEST GRID (wind on)60 MW235.6 MW31 May 2036not statedgate not printedAccepted to Connect

Receipt: MW and dates as printed in the SSEN Embedded Capacity Register, file dated 1 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
2025115.9 MW
2026299.8 MW
202719.9 MW
20351110 MW
2036160 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
BRACO WEST GRID (onshore wind, 110 MW)Onshore wind75 MW31 Oct 2035Accepted to Connect
BRACO WEST GRID (battery, 49.9 MW)Battery storage49.9 MW7 Jul 2026Accepted to Connect
BRACO WEST GRID (battery, 49.9 MW)Battery storage49.9 MW31 Dec 2026Accepted to Connect
BRACO WEST GRID (battery, 10 MW)Battery storage10 MWnot statedConnected
BRACO WEST GRID (solar, 9.9 MW)Solar9.9 MW30 Aug 2027Accepted to Connect
BRACO WEST GRID (solar, 15.9 MW)Solar9.9 MW30 Jun 2025Accepted to Connect
BRACO WEST GRID (onshore wind, 7.6 MW)Onshore wind7.6 MWnot statedConnected
BRACO WEST GRID (onshore wind, 4.3 MW)Onshore wind4.3 MWnot statedConnected
BRACO WEST GRID (onshore wind, 60 MW)Onshore wind1.2 MW31 May 2036Accepted to Connect
BRACO WEST GRID (hydro, 0.47 MW)Hydro and pumped storage0.48 MWnot statedConnected
BRACO WEST GRID (onshore wind, 0.31 MW)Onshore wind0.31 MWnot statedConnected
BRACO WEST GRID (solar, 4 MW)Solar0 MWnot statedAccepted to Connect
BRACO WEST GRID (battery, 50 MW)Battery storage0 MWnot statedAccepted to Connect
BRACO WEST GRID (battery, 49.9 MW)Battery storage0 MWnot statedAccepted to Connect
BRACO WEST GRID (onshore wind, 9.2 MW)Onshore wind0 MWnot statedAccepted to Connect
BRACO WEST GRID (solar, 36.18 MW)Solar0 MWnot statedAccepted to Connect
BRACO WEST GRID (other, 10 MW)Other0 MWnot statedAccepted to Connect
BRACO WEST GRID (battery, 49.9 MW)Battery storage0 MWnot statedAccepted to Connect
BRACO WEST GRID (battery, 60 MW)Battery storage0 MWnot statedAccepted to Connect
BRACO WEST GRID (solar, 15.9 MW)Solar0 MWnot statedAccepted to Connect
BRACO WEST GRID (battery, 25 MW)Battery storage0 MWnot statedAccepted to Connect
BRACO WEST GRID (onshore wind, 45 MW)Onshore wind0 MWnot statedAccepted to Connect
BRACO WEST GRID (other, 10 MW)Other0 MWnot statedAccepted to Connect
BRACO WEST GRID (battery, 25 MW)Battery storage0 MWnot statedAccepted to Connect
BRACO WEST GRID (battery, 71.03 MW)Battery storage0 MWnot statedAccepted to Connect
BRACO WEST GRID (solar, 15.9 MW)Solar0 MWnot statedAccepted to Connect

Contains data from Scottish and Southern Electricity Networks, licensed under CC BY 4.0.