N84 Grid

BRAMLEY (THAT-AMES)

DNO substation.

Contracted here0.05 GWNot yet connected, as printed
Entries in the queue2entries with a printed MW
Earliest connection date30 Nov 2025Already passed, not yet connected

The queue, in order

Order calculated by N84
First in queue49.7 MW across the first 2 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
BRAMLEY (THAT-AMES) (hybrid)9 May 202330 Nov 202542.7 MW
BRAMLEY (THAT-AMES) (bess)28 Apr 202330 Apr 20277 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW25 MW50 MW2025: 43 MW2027: 50 MW20252026202750 MW
0 MW25 MW50 MW2025: 43 MW2027: 50 MW20252026202750 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
202542.7 MW
202749.7 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1BRAMLEY (THAT-AMES) (hybrid)42.7 MW0 MW30 Nov 2025not statedgate not printedAccepted to Connect
2BRAMLEY (THAT-AMES) (bess)7 MW42.7 MW30 Apr 2027not statedgate not printedAccepted to Connect

Receipt: MW and dates as printed in the SSEN Embedded Capacity Register, file dated 1 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
2025142.7 MW
202717 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
BRAMLEY (THAT-AMES) (hybrid, 42.7 MW)Hybrid42.7 MW30 Nov 2025Accepted to Connect
BRAMLEY (THAT-AMES) (other, 0.43 MW)Other0.43 MWnot statedConnected
BRAMLEY (THAT-AMES) (other, 0.28 MW)Other0.28 MWnot statedConnected
BRAMLEY (THAT-AMES) (other, 0.09 MW)Other0.09 MWnot statedConnected
BRAMLEY (THAT-AMES) (other, 0.05 MW)Other0.05 MWnot statedConnected
BRAMLEY (THAT-AMES) (battery, 7 MW)Battery storage0 MW30 Apr 2027Accepted to Connect

Contains data from Scottish and Southern Electricity Networks, licensed under CC BY 4.0.

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.