CHICHESTER

DNO substation.

Contracted here0.11 GWNot yet connected, as printed
Entries in the queue7entries with a printed MW
Earliest connection date30 Jul 2026Already passed, not yet connected

The queue, in order

Order calculated by N84
First in queue36.76 MW across the first 6 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
CHICHESTER (solar)4 May 202230 Jul 20263.5 MW
CHICHESTER (solar)5 Dec 202330 Jul 202615 MW
CHICHESTER (solar)2 Dec 20252 Dec 20260.02 MW
CHICHESTER (solar)31 Mar 202631 Mar 20270.19 MW
CHICHESTER (solar)5 May 20265 May 20270.05 MW
CHICHESTER (other)24 Nov 202330 Oct 203718 MW
CHICHESTER (bess)6 Dec 202430 Jan 203870.4 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW100 MW200 MW2026: 19 MW2027: 19 MW2037: 37 MW2038: 107 MW2026202820302032203420362038107 MW
0 MW100 MW200 MW2026: 19 MW2027: 19 MW2037: 37 MW2038: 107 MW2026203020342038107 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
202618.52 MW
202718.76 MW
203736.76 MW
2038107.16 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1CHICHESTER (solar)3.5 MW0 MW30 Jul 2026not statedgate not printedAccepted to Connect
2CHICHESTER (solar)15 MW3.5 MW30 Jul 2026not statedgate not printedAccepted to Connect
3CHICHESTER (solar)0.02 MW18.5 MW2 Dec 2026not statedgate not printedAccepted to Connect
4CHICHESTER (solar)0.19 MW18.52 MW31 Mar 2027not statedgate not printedAccepted to Connect
5CHICHESTER (solar)0.05 MW18.71 MW5 May 2027not statedgate not printedAccepted to Connect
6CHICHESTER (other)18 MW18.76 MW30 Oct 2037not statedgate not printedAccepted to Connect
7CHICHESTER (bess)70.4 MW36.76 MW30 Jan 2038not statedgate not printedAccepted to Connect

Receipt: MW and dates as printed in the SSEN Embedded Capacity Register, file dated 1 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
2026318.52 MW
202720.24 MW
2037118 MW
2038170.4 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
CHICHESTER (battery, 70.4 MW)Battery storage70 MW30 Jan 2038Accepted to Connect
CHICHESTER (solar, 15 MW)Solar15 MW30 Jul 2026Accepted to Connect
CHICHESTER (gas, 6.65 MW)Gas6.65 MWnot statedConnected
CHICHESTER (other, 18 MW)Other5 MW30 Oct 2037Accepted to Connect
CHICHESTER (solar, 4 MW)Solar4 MWnot statedConnected
CHICHESTER (solar, 3.5 MW)Solar3.5 MW30 Jul 2026Accepted to Connect
CHICHESTER (biomass, 1.9 MW)Biomass and waste1.9 MWnot statedConnected
CHICHESTER (other, 0.95 MW)Other0.95 MWnot statedConnected
CHICHESTER (gas, 1.14 MW)Gas0.67 MWnot statedConnected
CHICHESTER (solar, 0.05 MW)Solar0.28 MW5 May 2027Accepted to Connect
CHICHESTER (solar, 0.19 MW)Solar0.28 MW31 Mar 2027Accepted to Connect
CHICHESTER (solar, 0.24 MW)Solar0.24 MWnot statedConnected
CHICHESTER (other, 0.2 MW)Other0.2 MWnot statedConnected
CHICHESTER (other, 0.36 MW)Other0.14 MWnot statedConnected
CHICHESTER (solar, 0.02 MW)Solar0.02 MW2 Dec 2026Accepted to Connect
CHICHESTER (battery, 52.25 MW)Battery storage0 MWnot statedAccepted to Connect
CHICHESTER (solar, 0.23 MW)Solar0 MWnot statedAccepted to Connect
CHICHESTER (biomass, 30 MW)Biomass and waste0 MWnot statedAccepted to Connect
CHICHESTER (battery, 50.16 MW)Battery storage0 MWnot statedAccepted to Connect
CHICHESTER (solar, 6 MW)Solar0 MWnot statedAccepted to Connect
CHICHESTER (gas, 0.7 MW)Gas0 MWnot statedAccepted to Connect
CHICHESTER (other, 49.9 MW)Other0 MW31 Oct 2037Accepted to Connect
CHICHESTER (solar, 15 MW)Solar0 MWnot statedAccepted to Connect
CHICHESTER (solar, 15 MW)Solar0 MWnot statedAccepted to Connect

Contains data from Scottish and Southern Electricity Networks, licensed under CC BY 4.0.