The queue, in order
Dates in the queue
From the earliest date we hold to the connection date printed, in queue order
- CHIPPENHAM (hybrid)
24 Jan 2025 to 24 Jan 2026, date already passed (gate not printed) - CHIPPENHAM (solar)
9 Jun 2022 to 22 Oct 2027 (gate not printed) - CHIPPENHAM (solar)
1 Aug 2022 to 15 Nov 2037 (gate not printed)
Table view
| Project | From | Connection date | MW |
|---|---|---|---|
| CHIPPENHAM (hybrid) | 24 Jan 2025 | 24 Jan 2026 | 25 MW |
| CHIPPENHAM (solar) | 9 Jun 2022 | 22 Oct 2027 | 40 MW |
| CHIPPENHAM (solar) | 1 Aug 2022 | 15 Nov 2037 | 23 MW |
Contracted MW as dates arrive
Running total by connection year, years to scale
Table view
| Year | Cumulative MW |
|---|---|
| 2026 | 25 MW |
| 2027 | 65 MW |
| 2037 | 88 MW |
Queue
| Placecalculated by N84 | Project | MW (as published) | MW ahead (N84 order) | Connection date | Gate | Order group | Status (as printed) |
|---|---|---|---|---|---|---|---|
| 1 | CHIPPENHAM (hybrid) | 25 MW | 0 MW | 24 Jan 2026 | not stated | gate not printed | Accepted to Connect |
| 2 | CHIPPENHAM (solar) | 40 MW | 25 MW | 22 Oct 2027 | not stated | gate not printed | Accepted to Connect |
| 3 | CHIPPENHAM (solar) | 23 MW | 65 MW | 15 Nov 2037 | not stated | gate not printed | Accepted to Connect |
| 4 | CHIPPENHAM (other) | 40 MW | 88 MW | not stated | not stated | gate not printed | Accepted to Connect |
Receipt: MW and dates as printed in the SSEN Embedded Capacity Register, file dated 1 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order
| Year (MW effective from) | Projects | MW |
|---|---|---|
| 2026 | 1 | 25 MW |
| 2027 | 1 | 40 MW |
| 2037 | 1 | 23 MW |
| not stated | 1 | 40 MW |
Projects recorded at this site
| Project (as published) | Technology | MW | Connection date | Status (as printed) |
|---|---|---|---|---|
| CHIPPENHAM (other, 40 MW) | Other | 40 MW | not stated | Accepted to Connect |
| CHIPPENHAM (solar, 40 MW) | Solar | 40 MW | 22 Oct 2027 | Accepted to Connect |
| CHIPPENHAM (solar, 23 MW) | Solar | 23 MW | 15 Nov 2037 | Accepted to Connect |
| CHIPPENHAM (hybrid, 25 MW) | Hybrid | 15 MW | 24 Jan 2026 | Accepted to Connect |
| CHIPPENHAM (onshore wind, 11.4 MW) | Onshore wind | 11.4 MW | not stated | Connected |
| CHIPPENHAM (solar, 0 MW) | Solar | 0 MW | 28 Feb 2026 | Accepted to Connect |
| CHIPPENHAM (solar, 40 MW) | Solar | 0 MW | not stated | Accepted to Connect |
| CHIPPENHAM (solar, 10 MW) | Solar | 0 MW | not stated | Accepted to Connect |
| CHIPPENHAM (hybrid, 25 MW) | Hybrid | 0 MW | not stated | Accepted to Connect |
| CHIPPENHAM (solar, 23 MW) | Solar | 0 MW | not stated | Accepted to Connect |
| CHIPPENHAM (solar, 40 MW) | Solar | 0 MW | 31 Oct 2028 | Accepted to Connect |
| CHIPPENHAM (solar, 0 MW) | Solar | 0 MW | 28 Feb 2026 | Accepted to Connect |
| CHIPPENHAM (solar, 2.09 MW) | Solar | 0 MW | not stated | Accepted to Connect |
| CHIPPENHAM (solar, 0 MW) | Solar | 0 MW | 28 Feb 2026 | Accepted to Connect |
| CHIPPENHAM (hybrid, 0 MW) | Hybrid | 0 MW | 15 Nov 2037 | Accepted to Connect |
Contains data from Scottish and Southern Electricity Networks, licensed under CC BY 4.0.