N84 Grid

CHRISTCHURCH

DNO substation.

Contracted here0.09 GWNot yet connected, as printed
Entries in the queue3entries with a printed MW
Earliest connection date27 Nov 2025Already passed, not yet connected

The queue, in order

Order calculated by N84
First in queue88.44 MW across the first 3 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
CHRISTCHURCH (solar)7 Aug 202427 Nov 20250.44 MW
CHRISTCHURCH (solar)31 Mar 20226 Dec 203648 MW
CHRISTCHURCH (gas)12 Jun 202330 Dec 203640 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW50 MW100 MW2025: 0 MW2036: 88 MW20252027202920312033203688 MW
0 MW50 MW100 MW2025: 0 MW2036: 88 MW2025202820312034203688 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
20250.44 MW
203688.44 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1CHRISTCHURCH (solar)0.44 MW0 MW27 Nov 2025not statedgate not printedAccepted to Connect
2CHRISTCHURCH (solar)48 MW0.44 MW6 Dec 2036not statedgate not printedAccepted to Connect
3CHRISTCHURCH (gas)40 MW48.44 MW30 Dec 2036not statedgate not printedAccepted to Connect

Receipt: MW and dates as printed in the SSEN Embedded Capacity Register, file dated 1 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
202510.44 MW
2036288 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
CHRISTCHURCH (solar, 48 MW)Solar48 MW6 Dec 2036Accepted to Connect
CHRISTCHURCH (gas, 40 MW)Gas40 MW30 Dec 2036Accepted to Connect
CHRISTCHURCH (other, 1.43 MW)Other0.73 MWnot statedConnected
CHRISTCHURCH (solar, 0.44 MW)Solar0.44 MW27 Nov 2025Accepted to Connect
CHRISTCHURCH (other, 0.1 MW)Other0.1 MWnot statedConnected
CHRISTCHURCH (solar, 40 MW)Solar0 MWnot statedAccepted to Connect

Contains data from Scottish and Southern Electricity Networks, licensed under CC BY 4.0.

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.