N84 Grid

CLACHAN GRID

DNO substation.

Contracted here0.04 GWNot yet connected, as printed
Entries in the queue2entries with a printed MW
Earliest connection date30 Sep 2025Already passed, not yet connected

The queue, in order

Order calculated by N84
First in queue38.76 MW across the first 2 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

  • CLACHAN GRID (hydro)8 Jun 2023 to 30 Sep 2025, date already passed (gate not printed)
  • CLACHAN (wind on)4 Oct 2023 to 31 Oct 2030 (gate not printed)
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
CLACHAN GRID (hydro)8 Jun 202330 Sep 20250.42 MW
CLACHAN (wind on)4 Oct 202331 Oct 203038.34 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW20 MW40 MW2025: 0 MW2030: 39 MW20252026202720282029203039 MW
0 MW20 MW40 MW2025: 0 MW2030: 39 MW202520272029203039 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
20250.42 MW
203038.76 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1CLACHAN GRID (hydro)0.42 MW0 MW30 Sep 2025not statedgate not printedAccepted to Connect
2CLACHAN (wind on)38.34 MW0.42 MW31 Oct 2030not statedgate not printedAccepted to Connect

Receipt: MW and dates as printed in the SSEN Embedded Capacity Register, file dated 1 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
202510.42 MW
2030138.34 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
CLACHAN GRID (other, 43.7 MW)Other43.7 MWnot statedConnected
CLACHAN GRID (onshore wind, 38.34 MW)Onshore wind38.34 MW31 Oct 2030Accepted to Connect
CLACHAN GRID (hydro, 5.7 MW)Hydro and pumped storage5.7 MWnot statedConnected
CLACHAN GRID (onshore wind, 1.8 MW)Onshore wind1.8 MWnot statedConnected
CLACHAN GRID (other, 0.89 MW)Other0.89 MWnot statedConnected
CLACHAN GRID (hydro, 0.85 MW)Hydro and pumped storage0.86 MWnot statedConnected
CLACHAN GRID (other, 0.47 MW)Other0.43 MWnot statedConnected
CLACHAN GRID (hydro, 0.42 MW)Hydro and pumped storage0.42 MW30 Sep 2025Accepted to Connect
CLACHAN GRID (hydro, 0.38 MW)Hydro and pumped storage0.38 MWnot statedConnected
CLACHAN GRID (hydro, 0.1 MW)Hydro and pumped storage0.1 MWnot statedConnected

Contains data from Scottish and Southern Electricity Networks, licensed under CC BY 4.0.

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.