COWLEY GSP

DNO substation.

Contracted here0.33 GWNot yet connected, as printed
Entries in the queue7entries with a printed MW
Earliest connection date4 Nov 2025Already passed, not yet connected

The queue, in order

Order calculated by N84
First in queue239.85 MW across the first 6 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
COWLEY GSP (solar)15 Mar 20244 Nov 202550 MW
COWLEY GSP (other)18 Sep 202321 Nov 202550 MW
COWLEY GSP (solar)15 Mar 202430 Jan 202620 MW
COWLEY GSP (bess)6 Sep 201931 Oct 202620 MW
COWLEY GSP (bess)29 Jul 202123 Jun 202849.95 MW
COWLEY GSP (solar)16 Sep 202123 Jun 202849.9 MW
COWLEY GSP (bess)25 Apr 202530 Dec 203785.5 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW200 MW400 MW2025: 100 MW2026: 140 MW2028: 240 MW2037: 325 MW2025202720292031203320352037325 MW
0 MW200 MW400 MW2025: 100 MW2026: 140 MW2028: 240 MW2037: 325 MW2025202920332037325 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
2025100 MW
2026140 MW
2028239.85 MW
2037325.35 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1COWLEY GSP (solar)50 MW0 MW4 Nov 2025not statedgate not printedAccepted to Connect
2COWLEY GSP (other)50 MW50 MW21 Nov 2025not statedgate not printedAccepted to Connect
3COWLEY GSP (solar)20 MW100 MW30 Jan 2026not statedgate not printedAccepted to Connect
4COWLEY GSP (bess)20 MW120 MW31 Oct 2026not statedgate not printedAccepted to Connect
5COWLEY GSP (bess)49.95 MW140 MW23 Jun 2028not statedgate not printedAccepted to Connect
6COWLEY GSP (solar)49.9 MW189.95 MW23 Jun 2028not statedgate not printedAccepted to Connect
7COWLEY GSP (bess)85.5 MW239.85 MW30 Dec 2037not statedgate not printedAccepted to Connect

Receipt: MW and dates as printed in the SSEN Embedded Capacity Register, file dated 1 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
20252100 MW
2026240 MW
2028299.85 MW
2037185.5 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
COWLEY GSP (other, 95 MW)Other95 MWnot statedConnected
COWLEY GSP (battery, 85.5 MW)Battery storage85.5 MW30 Dec 2037Accepted to Connect
COWLEY GSP (solar, 50 MW)Solar50 MW4 Nov 2025Accepted to Connect
COWLEY GSP (battery, 49.95 MW)Battery storage49.95 MW23 Jun 2028Accepted to Connect
COWLEY GSP (other, 50 MW)Other49.9 MW21 Nov 2025Accepted to Connect
COWLEY GSP (solar, 49.9 MW)Solar49.9 MW23 Jun 2028Accepted to Connect
COWLEY GSP (solar, 20 MW)Solar20 MW30 Jan 2026Accepted to Connect
COWLEY GSP (battery, 20 MW)Battery storage13.5 MW31 Oct 2026Accepted to Connect
COWLEY GSP (solar, 21 MW)Solar0 MW23 Jun 2028Accepted to Connect
COWLEY GSP (solar, 20 MW)Solar0 MWnot statedAccepted to Connect
COWLEY GSP (solar, 50 MW)Solar0 MWnot statedAccepted to Connect
COWLEY GSP (battery, 101.2 MW)Battery storage0 MWnot statedAccepted to Connect
COWLEY GSP (battery, 101.2 MW)Battery storage0 MW11 Nov 2038Accepted to Connect
COWLEY GSP (solar, 99.8 MW)Solar0 MWnot statedAccepted to Connect

Contains data from Scottish and Southern Electricity Networks, licensed under CC BY 4.0.

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.