COXMOOR WOOD

DNO substation.

Contracted here0.17 GWNot yet connected, as printed
Entries in the queue3entries with a printed MW
Earliest connection date24 Apr 2026Already passed, not yet connected

The queue, in order

Order calculated by N84
First in queue169.35 MW across the first 3 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
COXMOOR WOOD (hybrid)24 Apr 202524 Apr 20269.9 MW
COXMOOR WOOD (bess)17 Sep 202430 Oct 2027100 MW
COXMOOR WOOD (other)22 Dec 202331 Oct 203759.45 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW100 MW200 MW2026: 10 MW2027: 110 MW2037: 169 MW202620282030203220342037169 MW
0 MW100 MW200 MW2026: 10 MW2027: 110 MW2037: 169 MW20262029203220352037169 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
20269.9 MW
2027109.9 MW
2037169.35 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1COXMOOR WOOD (hybrid)9.9 MW0 MW24 Apr 2026not statedgate not printedAccepted to Connect
2COXMOOR WOOD (bess)100 MW9.9 MW30 Oct 2027not statedgate not printedAccepted to Connect
3COXMOOR WOOD (other)59.45 MW109.9 MW31 Oct 2037not statedgate not printedAccepted to Connect

Receipt: MW and dates as printed in the SSEN Embedded Capacity Register, file dated 1 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
202619.9 MW
20271100 MW
2037159.45 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
COXMOOR WOOD (battery, 100 MW)Battery storage100 MW30 Oct 2027Accepted to Connect
COXMOOR WOOD (other, 59.45 MW)Other49.9 MW31 Oct 2037Accepted to Connect
COXMOOR WOOD (battery, 20 MW)Battery storage20 MWnot statedConnected
COXMOOR WOOD (hybrid, 9.9 MW)Hybrid9.9 MW24 Apr 2026Accepted to Connect
COXMOOR WOOD (other, 0.06 MW)Other0.06 MWnot statedConnected

Contains data from Scottish and Southern Electricity Networks, licensed under CC BY 4.0.