N84 Grid

DUNOON GRID

DNO substation.

Contracted here0.11 GWNot yet connected, as printed
Entries in the queue4entries with a printed MW
Earliest connection date22 Feb 2026Already passed, not yet connected

The queue, in order

Order calculated by N84
First in queue105.63 MW across the first 4 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
DUNOON GRID (hydro)11 Oct 201922 Feb 20260.45 MW
DUNOON GRID (bess)27 Apr 202231 Mar 202652.68 MW
DUNOON GRID (wind on)23 Feb 202630 Dec 20284.5 MW
DUNOON GRID (wind on)1 Feb 202230 May 203048 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW100 MW200 MW2026: 53 MW2028: 58 MW2030: 106 MW20262027202820292030106 MW
0 MW100 MW200 MW2026: 53 MW2028: 58 MW2030: 106 MW202620282030106 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
202653.13 MW
202857.63 MW
2030105.63 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1DUNOON GRID (hydro)0.45 MW0 MW22 Feb 2026not statedgate not printedAccepted to Connect
2DUNOON GRID (bess)52.68 MW0.45 MW31 Mar 2026not statedgate not printedAccepted to Connect
3DUNOON GRID (wind on)4.5 MW53.13 MW30 Dec 2028not statedgate not printedAccepted to Connect
4DUNOON GRID (wind on)48 MW57.63 MW30 May 2030not statedgate not printedAccepted to Connect

Receipt: MW and dates as printed in the SSEN Embedded Capacity Register, file dated 1 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
2026253.13 MW
202814.5 MW
2030148 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
DUNOON GRID (battery, 52.68 MW)Battery storage45 MW31 Mar 2026Accepted to Connect
DUNOON GRID (onshore wind, 48 MW)Onshore wind44 MW30 May 2030Accepted to Connect
DUNOON GRID (onshore wind, 27.55 MW)Onshore wind27.55 MWnot statedConnected
DUNOON GRID (hydro, 3.71 MW)Hydro and pumped storage3.71 MWnot statedConnected
DUNOON GRID (hydro, 3.71 MW)Hydro and pumped storage3.71 MWnot statedConnected
DUNOON GRID (hydro, 0.85 MW)Hydro and pumped storage0.86 MWnot statedConnected
DUNOON GRID (onshore wind, 4.5 MW)Onshore wind0.5 MW30 Dec 2028Accepted to Connect
DUNOON GRID (hydro, 0.45 MW)Hydro and pumped storage0.45 MW22 Feb 2026Accepted to Connect
DUNOON GRID (hydro, 0.28 MW)Hydro and pumped storage0.28 MWnot statedConnected
DUNOON GRID (hydro, 0.13 MW)Hydro and pumped storage0.13 MWnot statedConnected
DUNOON GRID (hydro, 0.1 MW)Hydro and pumped storage0.1 MWnot statedConnected
DUNOON GRID (battery, 71.03 MW)Battery storage0 MWnot statedAccepted to Connect
DUNOON GRID (hydro, 0.49 MW)Hydro and pumped storage0 MWnot statedAccepted to Connect

Contains data from Scottish and Southern Electricity Networks, licensed under CC BY 4.0.

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.