DUNVEGAN GRID

DNO substation.

Contracted here0.06 GWNot yet connected, as printed
Entries in the queue3entries with a printed MW
Earliest connection date30 Sep 2027Date printed in the register

The queue, in order

Order calculated by N84
First in queue60.9 MW across the first 3 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
DUNVEGAN GRID (wind on)19 Jul 201930 Sep 20270.9 MW
DUNVEGAN GRID (wind on)3 May 201631 Jan 202825 MW
DUNVEGAN GRID (wind on)29 Mar 201930 Nov 202935 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW40 MW80 MW2027: 1 MW2028: 26 MW2029: 61 MW20272028202961 MW
0 MW40 MW80 MW2027: 1 MW2028: 26 MW2029: 61 MW20272028202961 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
20270.9 MW
202825.9 MW
202960.9 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1DUNVEGAN GRID (wind on)0.9 MW0 MW30 Sep 2027not statedgate not printedAccepted to Connect
2DUNVEGAN GRID (wind on)25 MW0.9 MW31 Jan 2028not statedgate not printedAccepted to Connect
3DUNVEGAN GRID (wind on)35 MW25.9 MW30 Nov 2029not statedgate not printedAccepted to Connect

Receipt: MW and dates as printed in the SSEN Embedded Capacity Register, file dated 1 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
202710.9 MW
2028125 MW
2029135 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
DUNVEGAN GRID (onshore wind, 28.02 MW)Onshore wind28.03 MWnot statedConnected
DUNVEGAN GRID (onshore wind, 35 MW)Onshore wind25 MW30 Nov 2029Accepted to Connect
DUNVEGAN GRID (onshore wind, 25 MW)Onshore wind25 MW31 Jan 2028Accepted to Connect
DUNVEGAN GRID (onshore wind, 0.9 MW)Onshore wind0.9 MW30 Sep 2027Accepted to Connect
DUNVEGAN GRID (onshore wind, 0.09 MW)Onshore wind0 MWnot statedConnected
DUNVEGAN GRID (onshore wind, 40.8 MW)Onshore wind0 MWnot statedAccepted to Connect
DUNVEGAN GRID (onshore wind, 45 MW)Onshore wind0 MWnot statedAccepted to Connect

Contains data from Scottish and Southern Electricity Networks, licensed under CC BY 4.0.