N84 Grid

ELGIN GRID

DNO substation.

Contracted here0.52 GWNot yet connected, as printed
Entries in the queue7entries with a printed MW
Earliest connection date16 Oct 2025Already passed, not yet connected

The queue, in order

Order calculated by N84
First in queue342.79 MW across the first 6 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
ELGIN GRID (solar)16 Oct 202416 Oct 20254.95 MW
ELGIN GRID (solar)6 May 202228 Feb 202799.8 MW
ELGIN GRID (bess)19 Mar 202431 Oct 202830 MW
ELGIN GRID (bess)3 Jan 202431 Oct 203052.68 MW
ELGIN GRID (bess)6 Nov 202430 Sep 2031105.36 MW
ELGIN GRID (hybrid)3 Oct 202530 Apr 203250 MW
ELGIN GRID (hybrid)16 Dec 202430 Jun 2032180 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW400 MW800 MW2025: 5 MW2027: 105 MW2028: 135 MW2030: 187 MW2031: 293 MW2032: 523 MW20252026202720282029203020312032523 MW
0 MW400 MW800 MW2025: 5 MW2027: 105 MW2028: 135 MW2030: 187 MW2031: 293 MW2032: 523 MW2025202720292032523 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
20254.95 MW
2027104.75 MW
2028134.75 MW
2030187.43 MW
2031292.79 MW
2032522.79 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1ELGIN GRID (solar)4.95 MW0 MW16 Oct 2025not statedgate not printedAccepted to Connect
2ELGIN GRID (solar)99.8 MW4.95 MW28 Feb 2027not statedgate not printedAccepted to Connect
3ELGIN GRID (bess)30 MW104.75 MW31 Oct 2028not statedgate not printedAccepted to Connect
4ELGIN GRID (bess)52.68 MW134.75 MW31 Oct 2030not statedgate not printedAccepted to Connect
5ELGIN GRID (bess)105.36 MW187.43 MW30 Sep 2031not statedgate not printedAccepted to Connect
6ELGIN GRID (hybrid)50 MW292.79 MW30 Apr 2032not statedgate not printedAccepted to Connect
7ELGIN GRID (hybrid)180 MW342.79 MW30 Jun 2032not statedgate not printedAccepted to Connect

Receipt: MW and dates as printed in the SSEN Embedded Capacity Register, file dated 1 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
202514.95 MW
2027199.8 MW
2028130 MW
2030152.68 MW
20311105.36 MW
20322230 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
ELGIN GRID (hybrid, 180 MW)Hybrid60 MW30 Jun 2032Accepted to Connect
ELGIN GRID (hybrid, 50 MW)Hybrid52.63 MW30 Apr 2032Accepted to Connect
ELGIN GRID (battery, 52.68 MW)Battery storage50 MW31 Oct 2030Accepted to Connect
ELGIN GRID (solar, 99.8 MW)Solar49.9 MW28 Feb 2027Accepted to Connect
ELGIN GRID (battery, 105.36 MW)Battery storage40 MW30 Sep 2031Accepted to Connect
ELGIN GRID (battery, 30 MW)Battery storage30 MW31 Oct 2028Accepted to Connect
ELGIN GRID (battery, 52.68 MW)Battery storage0 MW31 Dec 2029Accepted to Connect
ELGIN GRID (solar, 4.95 MW)Solar0 MW16 Oct 2025Accepted to Connect
ELGIN GRID (other, 30 MW)Other0 MWnot statedAccepted to Connect
ELGIN GRID (hybrid, 50 MW)Hybrid0 MW30 Apr 2032Accepted to Connect
ELGIN GRID (onshore wind, 35 MW)Onshore wind0 MWnot statedAccepted to Connect
ELGIN GRID (solar, 40 MW)Solar0 MW1 Jul 2027Accepted to Connect
ELGIN GRID (other, 52.68 MW)Other0 MWnot statedAccepted to Connect
ELGIN GRID (other, 30 MW)Other0 MWnot statedAccepted to Connect
ELGIN GRID (other, 52.68 MW)Other0 MWnot statedAccepted to Connect

Contains data from Scottish and Southern Electricity Networks, licensed under CC BY 4.0.

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.