The queue, in order
Dates in the queue
From the earliest date we hold to the connection date printed, in queue order
- GREMISTA 11KV SWITCHROOM (wind on)
14 Apr 2025 to 14 Apr 2026, date already passed (gate not printed) - GREMISTA 11KV SWITCHROOM (wind on)
17 May 2022 to 30 Jun 2026, date already passed (gate not printed)
Table view
| Project | From | Connection date | MW |
|---|---|---|---|
| GREMISTA 11KV SWITCHROOM (wind on) | 14 Apr 2025 | 14 Apr 2026 | 2.3 MW |
| GREMISTA 11KV SWITCHROOM (wind on) | 17 May 2022 | 30 Jun 2026 | 2.3 MW |
Contracted MW as dates arrive
Running total by connection year, years to scale
Table view
| Year | Cumulative MW |
|---|---|
| 2026 | 4.6 MW |
Queue
| Placecalculated by N84 | Project | MW (as published) | MW ahead (N84 order) | Connection date | Gate | Order group | Status (as printed) |
|---|---|---|---|---|---|---|---|
| 1 | GREMISTA 11KV SWITCHROOM (wind on) | 2.3 MW | 0 MW | 14 Apr 2026 | not stated | gate not printed | Accepted to Connect |
| 2 | GREMISTA 11KV SWITCHROOM (wind on) | 2.3 MW | 2.3 MW | 30 Jun 2026 | not stated | gate not printed | Accepted to Connect |
Receipt: MW and dates as printed in the SSEN Embedded Capacity Register, file dated 1 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order
| Year (MW effective from) | Projects | MW |
|---|---|---|
| 2026 | 2 | 4.6 MW |
Projects recorded at this site
| Project (as published) | Technology | MW | Connection date | Status (as printed) |
|---|---|---|---|---|
| GREMISTA 11KV SWITCHROOM (onshore wind, 3 MW) | Onshore wind | 3 MW | not stated | Connected |
| GREMISTA 11KV SWITCHROOM (onshore wind, 2.3 MW) | Onshore wind | 2.3 MW | 30 Jun 2026 | Accepted to Connect |
| GREMISTA 11KV SWITCHROOM (onshore wind, 2.3 MW) | Onshore wind | 2.3 MW | 14 Apr 2026 | Accepted to Connect |
| GREMISTA 11KV SWITCHROOM (onshore wind, 0.47 MW) | Onshore wind | 0.48 MW | not stated | Connected |
| GREMISTA 11KV SWITCHROOM (onshore wind, 0.9 MW) | Onshore wind | 0 MW | not stated | Accepted to Connect |
| GREMISTA 11KV SWITCHROOM (biomass, 5.89 MW) | Biomass and waste | 0 MW | not stated | Connected |
Contains data from Scottish and Southern Electricity Networks, licensed under CC BY 4.0.