GREMISTA 11KV SWITCHROOM

DNO substation.

Contracted here0.00 GWNot yet connected, as printed
Entries in the queue2entries with a printed MW
Earliest connection date14 Apr 2026Already passed, not yet connected

The queue, in order

Order calculated by N84
First in queue4.6 MW across the first 2 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
GREMISTA 11KV SWITCHROOM (wind on)14 Apr 202514 Apr 20262.3 MW
GREMISTA 11KV SWITCHROOM (wind on)17 May 202230 Jun 20262.3 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW3 MW5 MW2026: 5 MW20265 MW
0 MW3 MW5 MW2026: 5 MW20265 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
20264.6 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1GREMISTA 11KV SWITCHROOM (wind on)2.3 MW0 MW14 Apr 2026not statedgate not printedAccepted to Connect
2GREMISTA 11KV SWITCHROOM (wind on)2.3 MW2.3 MW30 Jun 2026not statedgate not printedAccepted to Connect

Receipt: MW and dates as printed in the SSEN Embedded Capacity Register, file dated 1 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
202624.6 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
GREMISTA 11KV SWITCHROOM (onshore wind, 3 MW)Onshore wind3 MWnot statedConnected
GREMISTA 11KV SWITCHROOM (onshore wind, 2.3 MW)Onshore wind2.3 MW30 Jun 2026Accepted to Connect
GREMISTA 11KV SWITCHROOM (onshore wind, 2.3 MW)Onshore wind2.3 MW14 Apr 2026Accepted to Connect
GREMISTA 11KV SWITCHROOM (onshore wind, 0.47 MW)Onshore wind0.48 MWnot statedConnected
GREMISTA 11KV SWITCHROOM (onshore wind, 0.9 MW)Onshore wind0 MWnot statedAccepted to Connect
GREMISTA 11KV SWITCHROOM (biomass, 5.89 MW)Biomass and waste0 MWnot statedConnected