N84 Grid

INVERNESS GRID

DNO substation.

Contracted here0.09 GWNot yet connected, as printed
Entries in the queue3entries with a printed MW
Earliest connection date31 Dec 2025Already passed, not yet connected

The queue, in order

Order calculated by N84
First in queue89.8 MW across the first 3 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
INVERNESS GRID (bess)13 Jun 202231 Dec 202550 MW
INVERNESS GRID (other)12 Apr 202431 May 202710 MW
INVERNESS (other)16 Apr 202431 Oct 202729.8 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW50 MW100 MW2025: 50 MW2027: 90 MW20252026202790 MW
0 MW50 MW100 MW2025: 50 MW2027: 90 MW20252026202790 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
202550 MW
202789.8 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1INVERNESS GRID (bess)50 MW0 MW31 Dec 2025not statedgate not printedAccepted to Connect
2INVERNESS GRID (other)10 MW50 MW31 May 2027not statedgate not printedAccepted to Connect
3INVERNESS (other)29.8 MW60 MW31 Oct 2027not statedgate not printedAccepted to Connect

Receipt: MW and dates as printed in the SSEN Embedded Capacity Register, file dated 1 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
2025150 MW
2027239.8 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
INVERNESS GRID (onshore wind, 60 MW)Onshore wind60 MWnot statedConnected
INVERNESS GRID (battery, 50 MW)Battery storage49.9 MW31 Dec 2025Accepted to Connect
INVERNESS GRID (other, 10 MW)Other9.9 MW31 May 2027Accepted to Connect
INVERNESS GRID (other, 29.8 MW)Other9.9 MW31 Oct 2027Accepted to Connect
INVERNESS GRID (onshore wind, 3.23 MW)Onshore wind3.23 MWnot statedConnected
INVERNESS GRID (solar, 2.28 MW)Solar2.28 MWnot statedConnected
INVERNESS GRID (hydro, 0.52 MW)Hydro and pumped storage0.52 MWnot statedConnected
INVERNESS GRID (other, 0.47 MW)Other0.48 MWnot statedConnected
INVERNESS GRID (other, 0.47 MW)Other0.48 MWnot statedConnected
INVERNESS GRID (hydro, 0.33 MW)Hydro and pumped storage0.33 MWnot statedConnected
INVERNESS GRID (hydro, 0.24 MW)Hydro and pumped storage0.24 MWnot statedConnected
INVERNESS GRID (solar, 0.04 MW)Solar0 MWnot statedAccepted to Connect
INVERNESS GRID (hybrid, 93 MW)Hybrid0 MW31 Oct 2030Accepted to Connect
INVERNESS GRID (solar, 0.03 MW)Solar0 MW26 Dec 2025Accepted to Connect
INVERNESS GRID (solar, 0.21 MW)Solar0 MWnot statedAccepted to Connect