N84 Grid

KINTORE SUPERGRID

DNO substation.

Contracted here0.22 GWNot yet connected, as printed
Entries in the queue2entries with a printed MW
Earliest connection date28 Feb 2029Date printed in the register

The queue, in order

Order calculated by N84
First in queue220 MW across the first 2 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
KINTORE SUPERGRID (hybrid)18 Dec 202428 Feb 2029180 MW
KINTORE SUPERGRID (solar)5 Nov 202431 Jan 203240 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW125 MW250 MW2029: 180 MW2032: 220 MW2029203020312032220 MW
0 MW125 MW250 MW2029: 180 MW2032: 220 MW2029203020312032220 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
2029180 MW
2032220 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1KINTORE SUPERGRID (hybrid)180 MW0 MW28 Feb 2029not statedgate not printedAccepted to Connect
2KINTORE SUPERGRID (solar)40 MW180 MW31 Jan 2032not statedgate not printedAccepted to Connect

Receipt: MW and dates as printed in the SSEN Embedded Capacity Register, file dated 1 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
20291180 MW
2032140 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
KINTORE SUPERGRID (hybrid, 180 MW)Hybrid60 MW28 Feb 2029Accepted to Connect
KINTORE SUPERGRID (solar, 40 MW)Solar40 MW31 Jan 2032Accepted to Connect

Contains data from Scottish and Southern Electricity Networks, licensed under CC BY 4.0.

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.