KNOWL HILL

DNO substation.

Contracted here0.02 GWNot yet connected, as printed
Entries in the queue2entries with a printed MW
Earliest connection date9 Jan 2026Already passed, not yet connected

The queue, in order

Order calculated by N84
First in queue18.85 MW across the first 2 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

  • KNOWL HILL (solar)9 Jan 2025 to 9 Jan 2026, date already passed (gate not printed)
  • KNOWL HILL (solar)25 Jun 2024 to 31 Oct 2037 (gate not printed)
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
KNOWL HILL (solar)9 Jan 20259 Jan 20261 MW
KNOWL HILL (solar)25 Jun 202431 Oct 203717.85 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW10 MW20 MW2026: 1 MW2037: 19 MW20262028203020322034203719 MW
0 MW10 MW20 MW2026: 1 MW2037: 19 MW2026202920322035203719 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
20261 MW
203718.85 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1KNOWL HILL (solar)1 MW0 MW9 Jan 2026not statedgate not printedAccepted to Connect
2KNOWL HILL (solar)17.85 MW1 MW31 Oct 2037not statedgate not printedAccepted to Connect

Receipt: MW and dates as printed in the SSEN Embedded Capacity Register, file dated 1 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
202611 MW
2037117.85 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
KNOWL HILL (solar, 17.85 MW)Solar17.85 MW31 Oct 2037Accepted to Connect
KNOWL HILL (solar, 1 MW)Solar0.65 MW9 Jan 2026Accepted to Connect
KNOWL HILL (solar, 1 MW)Solar0 MWnot statedAccepted to Connect

Contains data from Scottish and Southern Electricity Networks, licensed under CC BY 4.0.

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.