N84 Grid

LOVEDEAN GSP

DNO substation.

Contracted here0.20 GWNot yet connected, as printed
Entries in the queue2entries with a printed MW
Earliest connection date30 Oct 2037Date printed in the register

The queue, in order

Order calculated by N84
First in queue200.8 MW across the first 2 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
LOVEDEAN GSP (bess)26 Nov 202430 Oct 2037100.8 MW
LOVEDEAN (bess)27 Mar 202531 Dec 2038100 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW125 MW250 MW2037: 101 MW2038: 201 MW20372038201 MW
0 MW125 MW250 MW2037: 101 MW2038: 201 MW20372038201 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
2037100.8 MW
2038200.8 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1LOVEDEAN GSP (bess)100.8 MW0 MW30 Oct 2037not statedgate not printedAccepted to Connect
2LOVEDEAN (bess)100 MW100.8 MW31 Dec 2038not statedgate not printedAccepted to Connect

Receipt: MW and dates as printed in the SSEN Embedded Capacity Register, file dated 1 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
20371100.8 MW
20381100 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
LOVEDEAN GSP (battery, 100 MW)Battery storage105.26 MW31 Dec 2038Accepted to Connect
LOVEDEAN GSP (battery, 100.8 MW)Battery storage99.9 MW30 Oct 2037Accepted to Connect
LOVEDEAN GSP (other, 20 MW)Other20 MWnot statedConnected
LOVEDEAN GSP (other, 1 MW)Other1 MWnot statedConnected
LOVEDEAN GSP (other, 0.23 MW)Other0.23 MWnot statedConnected
LOVEDEAN GSP (other, 0.12 MW)Other0.12 MWnot statedConnected
LOVEDEAN GSP (solar, 0.11 MW)Solar0.08 MWnot statedConnected
LOVEDEAN GSP (other, 0.07 MW)Other0.07 MWnot statedConnected
LOVEDEAN GSP (battery, 57 MW)Battery storage0 MWnot statedAccepted to Connect
LOVEDEAN GSP (solar, 92.4 MW)Solar0 MWnot statedAccepted to Connect
LOVEDEAN GSP (other, 45.6 MW)Other0 MWnot statedAccepted to Connect
LOVEDEAN GSP (solar, 3 MW)Solar0 MWnot statedAccepted to Connect
LOVEDEAN GSP (battery, 100 MW)Battery storage0 MWnot statedAccepted to Connect
LOVEDEAN GSP (battery, 57 MW)Battery storage0 MWnot statedAccepted to Connect
LOVEDEAN GSP (battery, 57 MW)Battery storage0 MWnot statedAccepted to Connect
LOVEDEAN GSP (solar, 0.23 MW)Solar0 MWnot statedAccepted to Connect
LOVEDEAN GSP (battery, 57 MW)Battery storage0 MWnot statedAccepted to Connect
LOVEDEAN GSP (other, 50.16 MW)Other0 MWnot statedAccepted to Connect

Contains data from Scottish and Southern Electricity Networks, licensed under CC BY 4.0.

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.