N84 Grid

LYNDHURST GRID

DNO substation.

Contracted here0.11 GWNot yet connected, as printed
Entries in the queue6entries with a printed MW
Earliest connection date22 May 2027Date printed in the register

The queue, in order

Order calculated by N84
First in queue111.79 MW across the first 6 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
LYNDHURST (solar)22 May 202622 May 20270.02 MW
LYNDHURST (solar)27 May 202627 May 20270.04 MW
LYNDHURST (solar)17 Aug 202617 Aug 20270.03 MW
LYNDHURST GRID (bess)4 Aug 202231 Oct 202749.9 MW
LYNDHURST GRID (solar)18 Mar 202531 Mar 203036.72 MW
LYNDHURST GRID (other)20 Mar 202331 Oct 203125.08 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW100 MW200 MW2027: 50 MW2030: 87 MW2031: 112 MW20272028202920302031112 MW
0 MW100 MW200 MW2027: 50 MW2030: 87 MW2031: 112 MW202720292031112 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
202749.99 MW
203086.71 MW
2031111.79 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1LYNDHURST (solar)0.02 MW0 MW22 May 2027not statedgate not printedAccepted to Connect
2LYNDHURST (solar)0.04 MW0.02 MW27 May 2027not statedgate not printedAccepted to Connect
3LYNDHURST (solar)0.03 MW0.06 MW17 Aug 2027not statedgate not printedAccepted to Connect
4LYNDHURST GRID (bess)49.9 MW0.09 MW31 Oct 2027not statedgate not printedAccepted to Connect
5LYNDHURST GRID (solar)36.72 MW49.99 MW31 Mar 2030not statedgate not printedAccepted to Connect
6LYNDHURST GRID (other)25.08 MW86.71 MW31 Oct 2031not statedgate not printedAccepted to Connect

Receipt: MW and dates as printed in the SSEN Embedded Capacity Register, file dated 1 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
2027449.99 MW
2030136.72 MW
2031125.08 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
LYNDHURST GRID (battery, 49.9 MW)Battery storage49.9 MW31 Oct 2027Accepted to Connect
LYNDHURST GRID (battery, 47.41 MW)Battery storage47.41 MWnot statedConnected
LYNDHURST GRID (solar, 36.72 MW)Solar36.72 MW31 Mar 2030Accepted to Connect
LYNDHURST GRID (other, 25.08 MW)Other20 MW31 Oct 2031Accepted to Connect
LYNDHURST GRID (hydro, 2.85 MW)Hydro and pumped storage2.85 MWnot statedConnected
LYNDHURST GRID (solar, 0.01 MW)Solar0.13 MW22 May 2027Accepted to Connect
LYNDHURST GRID (solar, 0.04 MW)Solar0.04 MW27 May 2027Accepted to Connect
LYNDHURST GRID (solar, 0.03 MW)Solar0.03 MW17 Aug 2027Accepted to Connect
LYNDHURST GRID (solar, 35.52 MW)Solar0 MW30 Apr 2031Accepted to Connect
LYNDHURST GRID (other, 60 MW)Other0 MWnot statedAccepted to Connect
LYNDHURST GRID (other, 60 MW)Other0 MWnot statedAccepted to Connect
LYNDHURST GRID (battery, 49.5 MW)Battery storage0 MWnot statedAccepted to Connect
LYNDHURST GRID (solar, 50 MW)Solar0 MWnot statedAccepted to Connect
LYNDHURST GRID (other, 50 MW)Other0 MWnot statedAccepted to Connect
LYNDHURST GRID (other, 22 MW)Other0 MW30 Apr 2032Accepted to Connect
LYNDHURST GRID (solar, 50 MW)Solar0 MW31 Oct 2031Accepted to Connect
LYNDHURST GRID (battery, 49.9 MW)Battery storage0 MWnot statedAccepted to Connect

Contains data from Scottish and Southern Electricity Networks, licensed under CC BY 4.0.

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.