MANNINGTON GSP

DNO substation.

Contracted here0.68 GWNot yet connected, as printed
Entries in the queue9entries with a printed MW
Earliest connection date2 Jul 2025Already passed, not yet connected

The queue, in order

Order calculated by N84
First in queue452.26 MW across the first 6 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Unnamed site (solar)11 Jan 20212 Jul 20250.8 MW
MANNINGTON GSP (solar)21 Nov 202428 Jan 202750 MW
MANNINGTON BSP (solar)2 Jun 202529 Mar 203040 MW
MANNINGTON BSP (solar)17 Jun 202519 Jul 203061.56 MW
MANNINGTON (bess)4 Oct 202430 Jul 2030200 MW
MANNINGTON (bess)3 Apr 202530 Dec 203099.9 MW
MANNINGTON (gas)16 Jun 20226 Dec 203627.05 MW
MANNINGTON GSP (bess)29 Mar 202312 Dec 203699.9 MW
MANNINGTON (bess)31 Aug 202231 Dec 203698 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW400 MW800 MW2025: 1 MW2027: 51 MW2030: 452 MW2036: 677 MW202520272029203120332036677 MW
0 MW400 MW800 MW2025: 1 MW2027: 51 MW2030: 452 MW2036: 677 MW20252028203120342036677 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
20250.8 MW
202750.8 MW
2030452.26 MW
2036677.21 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Unnamed site (solar)0.8 MW0 MW2 Jul 2025not statedgate not printedAccepted to Connect
2MANNINGTON GSP (solar)50 MW0.8 MW28 Jan 2027not statedgate not printedAccepted to Connect
3MANNINGTON BSP (solar)40 MW50.8 MW29 Mar 2030not statedgate not printedAccepted to Connect
4MANNINGTON BSP (solar)61.56 MW90.8 MW19 Jul 2030not statedgate not printedAccepted to Connect
5MANNINGTON (bess)200 MW152.36 MW30 Jul 2030not statedgate not printedAccepted to Connect
6MANNINGTON (bess)99.9 MW352.36 MW30 Dec 2030not statedgate not printedAccepted to Connect
7MANNINGTON (gas)27.05 MW452.26 MW6 Dec 2036not statedgate not printedAccepted to Connect
8MANNINGTON GSP (bess)99.9 MW479.31 MW12 Dec 2036not statedgate not printedAccepted to Connect
9MANNINGTON (bess)98 MW579.21 MW31 Dec 2036not statedgate not printedAccepted to Connect

Receipt: MW and dates as printed in the SSEN Embedded Capacity Register, file dated 1 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
202510.8 MW
2027150 MW
20304401.46 MW
20363224.95 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
MANNINGTON GSP (battery, 200 MW)Battery storage200 MW30 Jul 2030Accepted to Connect
MANNINGTON GSP (battery, 99.9 MW)Battery storage99.9 MW30 Dec 2030Accepted to Connect
MANNINGTON GSP (battery, 99.9 MW)Battery storage99.9 MW12 Dec 2036Accepted to Connect
MANNINGTON GSP (battery, 98 MW)Battery storage98 MW31 Dec 2036Accepted to Connect
MANNINGTON GSP (solar, 61.56 MW)Solar61.56 MW19 Jul 2030Accepted to Connect
MANNINGTON GSP (solar, 50 MW)Solar49.9 MW28 Jan 2027Accepted to Connect
MANNINGTON GSP (battery, 47.02 MW)Battery storage47.03 MWnot statedConnected
MANNINGTON GSP (solar, 40 MW)Solar40 MW29 Mar 2030Accepted to Connect
MANNINGTON GSP (gas, 27.05 MW)Gas27.05 MW6 Dec 2036Accepted to Connect
MANNINGTON GSP (other, 19 MW)Other19 MWnot statedConnected
MANNINGTON GSP (solar, 0.8 MW)Solar0.8 MW2 Jul 2025Accepted to Connect
MANNINGTON GSP (other, 1.11 MW)Other0.8 MWnot statedConnected
MANNINGTON GSP (other, 0.47 MW)Other0.48 MWnot statedConnected
MANNINGTON GSP (other, 0.3 MW)Other0.3 MWnot statedConnected
MANNINGTON GSP (solar, 0.19 MW)Solar0.19 MWnot statedConnected
MANNINGTON GSP (other, 0.19 MW)Other0.19 MWnot statedConnected
MANNINGTON GSP (other, 0.19 MW)Other0.19 MWnot statedConnected
MANNINGTON GSP (other, 0.17 MW)Other0.17 MWnot statedConnected
MANNINGTON GSP (other, 0.18 MW)Other0.12 MWnot statedConnected
MANNINGTON GSP (other, 0.11 MW)Other0.11 MWnot statedConnected
MANNINGTON GSP (other, 0.1 MW)Other0.1 MWnot statedConnected
MANNINGTON GSP (solar, 0.1 MW)Solar0.1 MWnot statedConnected
MANNINGTON GSP (other, 0.08 MW)Other0.08 MWnot statedConnected
MANNINGTON GSP (other, 0.06 MW)Other0.06 MWnot statedConnected
MANNINGTON GSP (solar, 13.2 MW)Solar0 MW20 Aug 2028Accepted to Connect
MANNINGTON GSP (battery, 98 MW)Battery storage0 MWnot statedAccepted to Connect
MANNINGTON GSP (battery, 99.9 MW)Battery storage0 MWnot statedAccepted to Connect

Contains data from Scottish and Southern Electricity Networks, licensed under CC BY 4.0.

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.