N84 Grid

MELKSHAM GSP

DNO substation.

Contracted here0.66 GWNot yet connected, as printed
Entries in the queue9entries with a printed MW
Earliest connection date9 Apr 2025Already passed, not yet connected

The queue, in order

Order calculated by N84
First in queue390.48 MW across the first 6 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
MELKSHAM GSP (other)9 Apr 20249 Apr 202580 MW
MELKSHAM GSP (bess)7 Oct 20247 Oct 202555.91 MW
MELKSHAM GSP (hybrid)27 Oct 202029 Oct 202750 MW
MELKSHAM GSP (solar)9 Jun 202229 Oct 202740.32 MW
MELKSHAM GSP (solar)24 Mar 202329 Oct 202714.25 MW
MELKSHAM GSP (bess)30 Sep 202115 Oct 2037150 MW
MELKSHAM GSP (bess)6 Apr 202315 Nov 2037104.2 MW
MELKSHAM GSP (bess)12 Mar 202415 Nov 2037111.9 MW
MELKSHAM GRID (solar)5 Aug 202415 Nov 203749.9 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW400 MW800 MW2025: 136 MW2027: 240 MW2037: 656 MW2025202720292031203320352037656 MW
0 MW400 MW800 MW2025: 136 MW2027: 240 MW2037: 656 MW2025202920332037656 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
2025135.91 MW
2027240.48 MW
2037656.48 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1MELKSHAM GSP (other)80 MW0 MW9 Apr 2025not statedgate not printedAccepted to Connect
2MELKSHAM GSP (bess)55.91 MW80 MW7 Oct 2025not statedgate not printedAccepted to Connect
3MELKSHAM GSP (hybrid)50 MW135.91 MW29 Oct 2027not statedgate not printedAccepted to Connect
4MELKSHAM GSP (solar)40.32 MW185.91 MW29 Oct 2027not statedgate not printedAccepted to Connect
5MELKSHAM GSP (solar)14.25 MW226.23 MW29 Oct 2027not statedgate not printedAccepted to Connect
6MELKSHAM GSP (bess)150 MW240.48 MW15 Oct 2037not statedgate not printedAccepted to Connect
7MELKSHAM GSP (bess)104.2 MW390.48 MW15 Nov 2037not statedgate not printedAccepted to Connect
8MELKSHAM GSP (bess)111.9 MW494.68 MW15 Nov 2037not statedgate not printedAccepted to Connect
9MELKSHAM GRID (solar)49.9 MW606.58 MW15 Nov 2037not statedgate not printedAccepted to Connect

Receipt: MW and dates as printed in the SSEN Embedded Capacity Register, file dated 1 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
20252135.91 MW
20273104.57 MW
20374416 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
MELKSHAM GSP (battery, 150 MW)Battery storage150 MW15 Oct 2037Accepted to Connect
MELKSHAM GSP (battery, 104.2 MW)Battery storage99.9 MW15 Nov 2037Accepted to Connect
MELKSHAM GSP (battery, 111.9 MW)Battery storage99.9 MW15 Nov 2037Accepted to Connect
MELKSHAM GSP (other, 80 MW)Other70 MW9 Apr 2025Accepted to Connect
MELKSHAM GSP (hybrid, 50 MW)Hybrid50 MW29 Oct 2027Accepted to Connect
MELKSHAM GSP (other, 49.95 MW)Other49.95 MWnot statedConnected
MELKSHAM GSP (other, 49.95 MW)Other49.95 MWnot statedConnected
MELKSHAM GSP (solar, 49.9 MW)Solar49.9 MW15 Nov 2037Accepted to Connect
MELKSHAM GSP (solar, 40.32 MW)Solar40.32 MW29 Oct 2027Accepted to Connect
MELKSHAM GSP (solar, 14.25 MW)Solar14.25 MW29 Oct 2027Accepted to Connect
MELKSHAM GSP (other, 0.07 MW)Other0.07 MWnot statedConnected
MELKSHAM GSP (other, 129.9 MW)Other0 MW15 Nov 2037Accepted to Connect
MELKSHAM GSP (battery, 2.5 MW)Battery storage0 MWnot statedAccepted to Connect
MELKSHAM GSP (other, 50 MW)Other0 MWnot statedAccepted to Connect
MELKSHAM GSP (battery, 99.95 MW)Battery storage0 MWnot statedAccepted to Connect
MELKSHAM GSP (hybrid, 105.5 MW)Hybrid0 MW15 Nov 2037Accepted to Connect
MELKSHAM GSP (gas, 105.2 MW)Gas0 MWnot statedAccepted to Connect
MELKSHAM GSP (hybrid, 100 MW)Hybrid0 MWnot statedAccepted to Connect
MELKSHAM GSP (solar, 30 MW)Solar0 MWnot statedAccepted to Connect
MELKSHAM GSP (solar, 49.9 MW)Solar0 MWnot statedAccepted to Connect
MELKSHAM GSP (battery, 99.95 MW)Battery storage0 MWnot statedAccepted to Connect
MELKSHAM GSP (other, 50 MW)Other0 MWnot statedAccepted to Connect
MELKSHAM GSP (solar, 40 MW)Solar0 MWnot statedAccepted to Connect
MELKSHAM GSP (other, 105.2 MW)Other0 MWnot statedAccepted to Connect
MELKSHAM GSP (other, 104 MW)Other0 MW15 Nov 2037Accepted to Connect
MELKSHAM GSP (battery, 55.91 MW)Battery storage0 MW7 Oct 2025Accepted to Connect

Contains data from Scottish and Southern Electricity Networks, licensed under CC BY 4.0.

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.