The queue, in order
Dates in the queue
From the earliest date we hold to the connection date printed, in queue order
- MOUNT PLEASANT (wind on)
22 May 2025 to 22 May 2026, date already passed (gate not printed) - MOUNT PLEASANT (wind on)
20 Apr 2026 to 20 Apr 2027 (gate not printed)
Table view
| Project | From | Connection date | MW |
|---|---|---|---|
| MOUNT PLEASANT (wind on) | 22 May 2025 | 22 May 2026 | 0.45 MW |
| MOUNT PLEASANT (wind on) | 20 Apr 2026 | 20 Apr 2027 | 0.7 MW |
Contracted MW as dates arrive
Running total by connection year, years to scale
Table view
| Year | Cumulative MW |
|---|---|
| 2026 | 0.45 MW |
| 2027 | 1.15 MW |
Queue
| Placecalculated by N84 | Project | MW (as published) | MW ahead (N84 order) | Connection date | Gate | Order group | Status (as printed) |
|---|---|---|---|---|---|---|---|
| 1 | MOUNT PLEASANT (wind on) | 0.45 MW | 0 MW | 22 May 2026 | not stated | gate not printed | Accepted to Connect |
| 2 | MOUNT PLEASANT (wind on) | 0.7 MW | 0.45 MW | 20 Apr 2027 | not stated | gate not printed | Accepted to Connect |
Receipt: MW and dates as printed in the SSEN Embedded Capacity Register, file dated 1 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order
| Year (MW effective from) | Projects | MW |
|---|---|---|
| 2026 | 1 | 0.45 MW |
| 2027 | 1 | 0.7 MW |
Projects recorded at this site
| Project (as published) | Technology | MW | Connection date | Status (as printed) |
|---|---|---|---|---|
| MOUNT PLEASANT (onshore wind, 0.7 MW) | Onshore wind | 0.7 MW | 20 Apr 2027 | Accepted to Connect |
| MOUNT PLEASANT (onshore wind, 0.45 MW) | Onshore wind | 0.45 MW | 22 May 2026 | Accepted to Connect |
Contains data from Scottish and Southern Electricity Networks, licensed under CC BY 4.0.
Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.