The queue, in order
Dates in the queue
From the earliest date we hold to the connection date printed, in queue order
- NORRINGTON (bess)
23 Jan 2023 to 20 Feb 2025, date already passed (gate not printed) - NORRINGTON (bess)
6 Apr 2018 to 9 Apr 2026, date already passed (gate not printed) - NORRINGTON (gas)
19 May 2021 to 23 Oct 2026 (gate not printed) - NORRINGTON (bess)
26 Apr 2023 to 27 Jul 2027 (gate not printed) - NORRINGTON (solar)
29 Apr 2021 to 29 Oct 2027 (gate not printed) - NORRINGTON (solar)
18 Mar 2024 to 29 Oct 2027 (gate not printed) - NORRINGTON (hybrid)
10 Oct 2023 to 30 Nov 2028 (gate not printed) - NORRINGTON (solar)
10 Mar 2021 to 30 Oct 2037 (gate not printed) - NORRINGTON (bess)
6 May 2022 to 15 Nov 2037 (gate not printed) - NORRINGTON (hybrid)
18 Jul 2022 to 15 Nov 2037 (gate not printed) - NORRINGTON (bess)
1 Nov 2022 to 15 Nov 2037 (gate not printed)
Table view
| Project | From | Connection date | MW |
|---|---|---|---|
| NORRINGTON (bess) | 23 Jan 2023 | 20 Feb 2025 | 20 MW |
| NORRINGTON (bess) | 6 Apr 2018 | 9 Apr 2026 | 7 MW |
| NORRINGTON (gas) | 19 May 2021 | 23 Oct 2026 | 35.47 MW |
| NORRINGTON (bess) | 26 Apr 2023 | 27 Jul 2027 | 99.9 MW |
| NORRINGTON (solar) | 29 Apr 2021 | 29 Oct 2027 | 10 MW |
| NORRINGTON (solar) | 18 Mar 2024 | 29 Oct 2027 | 12 MW |
| NORRINGTON (hybrid) | 10 Oct 2023 | 30 Nov 2028 | 30 MW |
| NORRINGTON (solar) | 10 Mar 2021 | 30 Oct 2037 | 9.96 MW |
| NORRINGTON (bess) | 6 May 2022 | 15 Nov 2037 | 25.3 MW |
| NORRINGTON (hybrid) | 18 Jul 2022 | 15 Nov 2037 | 45 MW |
| NORRINGTON (bess) | 1 Nov 2022 | 15 Nov 2037 | 30 MW |
Contracted MW as dates arrive
Running total by connection year, years to scale
Table view
| Year | Cumulative MW |
|---|---|
| 2025 | 20 MW |
| 2026 | 62.47 MW |
| 2027 | 184.37 MW |
| 2028 | 214.37 MW |
| 2037 | 324.63 MW |
Queue
| Placecalculated by N84 | Project | MW (as published) | MW ahead (N84 order) | Connection date | Gate | Order group | Status (as printed) |
|---|---|---|---|---|---|---|---|
| 1 | NORRINGTON (bess) | 20 MW | 0 MW | 20 Feb 2025 | not stated | gate not printed | Accepted to Connect |
| 2 | NORRINGTON (bess) | 7 MW | 20 MW | 9 Apr 2026 | not stated | gate not printed | Accepted to Connect |
| 3 | NORRINGTON (gas) | 35.47 MW | 27 MW | 23 Oct 2026 | not stated | gate not printed | Accepted to Connect |
| 4 | NORRINGTON (bess) | 99.9 MW | 62.47 MW | 27 Jul 2027 | not stated | gate not printed | Accepted to Connect |
| 5 | NORRINGTON (solar) | 10 MW | 162.37 MW | 29 Oct 2027 | not stated | gate not printed | Accepted to Connect |
| 6 | NORRINGTON (solar) | 12 MW | 172.37 MW | 29 Oct 2027 | not stated | gate not printed | Accepted to Connect |
| 7 | NORRINGTON (hybrid) | 30 MW | 184.37 MW | 30 Nov 2028 | not stated | gate not printed | Accepted to Connect |
| 8 | NORRINGTON (solar) | 9.96 MW | 214.37 MW | 30 Oct 2037 | not stated | gate not printed | Accepted to Connect |
| 9 | NORRINGTON (bess) | 25.3 MW | 224.33 MW | 15 Nov 2037 | not stated | gate not printed | Accepted to Connect |
| 10 | NORRINGTON (hybrid) | 45 MW | 249.63 MW | 15 Nov 2037 | not stated | gate not printed | Accepted to Connect |
| 11 | NORRINGTON (bess) | 30 MW | 294.63 MW | 15 Nov 2037 | not stated | gate not printed | Accepted to Connect |
Receipt: MW and dates as printed in the SSEN Embedded Capacity Register, file dated 1 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order
| Year (MW effective from) | Projects | MW |
|---|---|---|
| 2025 | 1 | 20 MW |
| 2026 | 2 | 42.47 MW |
| 2027 | 3 | 121.9 MW |
| 2028 | 1 | 30 MW |
| 2037 | 4 | 110.26 MW |
Projects recorded at this site
| Project (as published) | Technology | MW | Connection date | Status (as printed) |
|---|---|---|---|---|
| NORRINGTON (battery, 99.9 MW) | Battery storage | 99.9 MW | 27 Jul 2027 | Accepted to Connect |
| NORRINGTON (hybrid, 30 MW) | Hybrid | 30 MW | 30 Nov 2028 | Accepted to Connect |
| NORRINGTON (battery, 30 MW) | Battery storage | 30 MW | 15 Nov 2037 | Accepted to Connect |
| NORRINGTON (gas, 35.47 MW) | Gas | 26.5 MW | 23 Oct 2026 | Accepted to Connect |
| NORRINGTON (battery, 25.3 MW) | Battery storage | 25.3 MW | 15 Nov 2037 | Accepted to Connect |
| NORRINGTON (hybrid, 45 MW) | Hybrid | 22.5 MW | 15 Nov 2037 | Accepted to Connect |
| NORRINGTON (hybrid, 20 MW) | Hybrid | 20 MW | not stated | Connected |
| NORRINGTON (battery, 20 MW) | Battery storage | 20 MW | 20 Feb 2025 | Accepted to Connect |
| NORRINGTON (solar, 12 MW) | Solar | 12 MW | 29 Oct 2027 | Accepted to Connect |
| NORRINGTON (solar, 10 MW) | Solar | 10 MW | 29 Oct 2027 | Accepted to Connect |
| NORRINGTON (solar, 9.96 MW) | Solar | 9.96 MW | 30 Oct 2037 | Accepted to Connect |
| NORRINGTON (battery, 7 MW) | Battery storage | 7 MW | 9 Apr 2026 | Accepted to Connect |
| NORRINGTON (gas, 110 MW) | Gas | 0 MW | 15 Nov 2037 | Accepted to Connect |
| NORRINGTON (solar) | Solar | 0 MW | not stated | Accepted to Connect |
| NORRINGTON (solar, 15.58 MW) | Solar | 0 MW | not stated | Accepted to Connect |
| NORRINGTON (battery, 99.9 MW) | Battery storage | 0 MW | not stated | Accepted to Connect |
| NORRINGTON (solar, 23 MW) | Solar | 0 MW | not stated | Accepted to Connect |
| NORRINGTON (battery, 30 MW) | Battery storage | 0 MW | not stated | Accepted to Connect |
| NORRINGTON (hybrid, 14.75 MW) | Hybrid | 0 MW | not stated | Accepted to Connect |
| NORRINGTON (gas, 50.01 MW) | Gas | 0 MW | not stated | Accepted to Connect |
| NORRINGTON (battery, 75.2 MW) | Battery storage | 0 MW | not stated | Accepted to Connect |
| NORRINGTON (battery, 20 MW) | Battery storage | 0 MW | not stated | Accepted to Connect |
| NORRINGTON (hybrid, 14.75 MW) | Hybrid | 0 MW | 15 Nov 2037 | Accepted to Connect |
| NORRINGTON (solar, 15.58 MW) | Solar | 0 MW | not stated | Accepted to Connect |
| NORRINGTON (solar, 40 MW) | Solar | 0 MW | not stated | Accepted to Connect |
| NORRINGTON (solar, 40 MW) | Solar | 0 MW | not stated | Accepted to Connect |
| NORRINGTON (solar, 40 MW) | Solar | 0 MW | not stated | Accepted to Connect |
| NORRINGTON (other, 100 MW) | Other | 0 MW | 15 Nov 2037 | Accepted to Connect |
| NORRINGTON (battery, 20 MW) | Battery storage | 0 MW | not stated | Accepted to Connect |
| NORRINGTON (solar, 20 MW) | Solar | 0 MW | not stated | Accepted to Connect |
| NORRINGTON (battery, 75.2 MW) | Battery storage | 0 MW | not stated | Accepted to Connect |
Contains data from Scottish and Southern Electricity Networks, licensed under CC BY 4.0.