N84 Grid

PETERHEAD GRANGE 11KV

DNO substation.

Contracted here0.25 GWNot yet connected, as printed
Entries in the queue10entries with a printed MW
Earliest connection date12 Jun 2025Already passed, not yet connected

The queue, in order

Order calculated by N84
First in queue44.24 MW across the first 6 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
PETERHEAD GRANGE 11KV (solar)12 Jun 202412 Jun 20250.06 MW
PETERHEAD GRANGE 11KV (solar)25 Jun 202531 Mar 20260.15 MW
PETERHEAD GRANGE 11KV (solar)16 May 20226 Apr 20260.19 MW
PETERHEAD GRANGE 11KV (solar)12 May 202512 May 20260.04 MW
PETERHEAD GRANGE 33KV (hybrid)16 Dec 20221 Oct 202643.75 MW
PETERHEAD GRANGE 11KV (solar)2 Jun 20262 Jun 20270.05 MW
PETERHEAD GRANGE 11KV (solar)2 Dec 202213 Sep 20280.23 MW
PETERHEAD GRANGE 33KV (hybrid)14 May 202531 May 203299.95 MW
PETERHEAD GRANGE (hybrid)14 May 202531 Oct 203250.16 MW
PETERHEAD GRANGE 33KV (wind off)4 Jul 202431 Oct 203351 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW125 MW250 MW2025: 0 MW2026: 44 MW2027: 44 MW2028: 44 MW2032: 195 MW2033: 246 MW20252027202920312033246 MW
0 MW125 MW250 MW2025: 0 MW2026: 44 MW2027: 44 MW2028: 44 MW2032: 195 MW2033: 246 MW2025202820312033246 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
20250.06 MW
202644.19 MW
202744.24 MW
202844.47 MW
2032194.58 MW
2033245.58 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1PETERHEAD GRANGE 11KV (solar)0.06 MW0 MW12 Jun 2025not statedgate not printedAccepted to Connect
2PETERHEAD GRANGE 11KV (solar)0.15 MW0.06 MW31 Mar 2026not statedgate not printedAccepted to Connect
3PETERHEAD GRANGE 11KV (solar)0.19 MW0.21 MW6 Apr 2026not statedgate not printedAccepted to Connect
4PETERHEAD GRANGE 11KV (solar)0.04 MW0.4 MW12 May 2026not statedgate not printedAccepted to Connect
5PETERHEAD GRANGE 33KV (hybrid)43.75 MW0.44 MW1 Oct 2026not statedgate not printedAccepted to Connect
6PETERHEAD GRANGE 11KV (solar)0.05 MW44.19 MW2 Jun 2027not statedgate not printedAccepted to Connect
7PETERHEAD GRANGE 11KV (solar)0.23 MW44.24 MW13 Sep 2028not statedgate not printedAccepted to Connect
8PETERHEAD GRANGE 33KV (hybrid)99.95 MW44.47 MW31 May 2032not statedgate not printedAccepted to Connect
9PETERHEAD GRANGE (hybrid)50.16 MW144.42 MW31 Oct 2032not statedgate not printedAccepted to Connect
10PETERHEAD GRANGE 33KV (wind off)51 MW194.58 MW31 Oct 2033not statedgate not printedAccepted to Connect

Receipt: MW and dates as printed in the SSEN Embedded Capacity Register, file dated 1 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
202510.06 MW
2026444.13 MW
202710.05 MW
202810.23 MW
20322150.11 MW
2033151 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
PETERHEAD GRANGE 11KV (hybrid, 99.95 MW)Hybrid52.53 MW31 May 2032Accepted to Connect
PETERHEAD GRANGE 11KV (offshore wind, 51 MW)Offshore wind50 MW31 Oct 2033Accepted to Connect
PETERHEAD GRANGE 11KV (hybrid, 43.75 MW)Hybrid35 MW1 Oct 2026Accepted to Connect
PETERHEAD GRANGE 11KV (onshore wind, 28.5 MW)Onshore wind28.5 MWnot statedConnected
PETERHEAD GRANGE 11KV (hybrid, 50.16 MW)Hybrid26.5 MW31 Oct 2032Accepted to Connect
PETERHEAD GRANGE 11KV (onshore wind, 0.81 MW)Onshore wind0.81 MWnot statedConnected
PETERHEAD GRANGE 11KV (solar, 0.23 MW)Solar0.23 MW13 Sep 2028Accepted to Connect
PETERHEAD GRANGE 11KV (other, 0.34 MW)Other0.22 MWnot statedConnected
PETERHEAD GRANGE 11KV (solar, 0.19 MW)Solar0.19 MW6 Apr 2026Accepted to Connect
PETERHEAD GRANGE 11KV (solar, 0.15 MW)Solar0.14 MW31 Mar 2026Accepted to Connect
PETERHEAD GRANGE 11KV (solar, 0.06 MW)Solar0.06 MW12 Jun 2025Accepted to Connect
PETERHEAD GRANGE 11KV (solar, 0.05 MW)Solar0.05 MW2 Jun 2027Accepted to Connect
PETERHEAD GRANGE 11KV (solar, 0.04 MW)Solar0.04 MW12 May 2026Accepted to Connect
PETERHEAD GRANGE 11KV (solar, 0.1 MW)Solar0 MW31 Mar 2025Accepted to Connect
PETERHEAD GRANGE 11KV (solar, 113.18 MW)Solar0 MWnot statedAccepted to Connect
PETERHEAD GRANGE 11KV (other, 61.46 MW)Other0 MWnot statedAccepted to Connect
PETERHEAD GRANGE 11KV (solar, 31.61 MW)Solar0 MWnot statedAccepted to Connect
PETERHEAD GRANGE 11KV (hybrid, 43.75 MW)Hybrid0 MWnot statedAccepted to Connect
PETERHEAD GRANGE 11KV (solar, 39.93 MW)Solar0 MW8 Aug 2034Accepted to Connect
PETERHEAD GRANGE 11KV (battery, 0.19 MW)Battery storage0 MW10 Jun 2026Accepted to Connect
PETERHEAD GRANGE 11KV (solar, 35 MW)Solar0 MWnot statedAccepted to Connect
PETERHEAD GRANGE 11KV (solar, 0.55 MW)Solar0 MWnot statedAccepted to Connect
PETERHEAD GRANGE 11KV (solar, 0.05 MW)Solar0 MW6 Feb 2027Accepted to Connect
PETERHEAD GRANGE 11KV (solar, 0.04 MW)Solar0 MW5 Dec 2026Accepted to Connect

Contains data from Scottish and Southern Electricity Networks, licensed under CC BY 4.0.

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.