N84 Grid

PETERSFIELD

DNO substation.

Contracted here0.04 GWNot yet connected, as printed
Entries in the queue2entries with a printed MW
Earliest connection date23 Jul 2025Already passed, not yet connected

The queue, in order

Order calculated by N84
First in queue36.08 MW across the first 2 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
PETERSFIELD (solar)23 Jul 202423 Jul 202536 MW
PETERSFIELD (solar)6 Jan 20266 Jan 20270.08 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW20 MW40 MW2025: 36 MW2027: 36 MW20252026202736 MW
0 MW20 MW40 MW2025: 36 MW2027: 36 MW20252026202736 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
202536 MW
202736.08 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1PETERSFIELD (solar)36 MW0 MW23 Jul 2025not statedgate not printedAccepted to Connect
2PETERSFIELD (solar)0.08 MW36 MW6 Jan 2027not statedgate not printedAccepted to Connect

Receipt: MW and dates as printed in the SSEN Embedded Capacity Register, file dated 1 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
2025136 MW
202710.08 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
PETERSFIELD (solar, 36 MW)Solar26 MW23 Jul 2025Accepted to Connect
PETERSFIELD (solar, 0.08 MW)Solar0.35 MW6 Jan 2027Accepted to Connect
PETERSFIELD (other, 0.47 MW)Other0.25 MWnot statedConnected
PETERSFIELD (other, 0.24 MW)Other0.24 MWnot statedConnected
PETERSFIELD (solar, 0.08 MW)Solar0 MW25 Nov 2026Accepted to Connect
PETERSFIELD (solar, 0.07 MW)Solar0 MW17 Nov 2026Accepted to Connect
PETERSFIELD (solar, 0.08 MW)Solar0 MW25 Nov 2026Accepted to Connect
PETERSFIELD (solar, 0.08 MW)Solar0 MW3 Sep 2026Accepted to Connect

Contains data from Scottish and Southern Electricity Networks, licensed under CC BY 4.0.

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.