The queue, in order
Dates in the queue
From the earliest date we hold to the connection date printed, in queue order
- ROTHIENORMAN (bess)
27 Jan 2022 to 6 May 2026, date already passed (gate not printed) - ROTHIENORMAN (bess)
4 Nov 2024 to 6 Nov 2026 (gate not printed) - ROTHIENORMAN (bess)
8 Sep 2023 to 30 Jun 2030 (gate not printed) - ROTHIENORMAN (bess)
19 Jan 2026 to 19 Jan 2031 (gate not printed)
Table view
| Project | From | Connection date | MW |
|---|---|---|---|
| ROTHIENORMAN (bess) | 27 Jan 2022 | 6 May 2026 | 57 MW |
| ROTHIENORMAN (bess) | 4 Nov 2024 | 6 Nov 2026 | 50 MW |
| ROTHIENORMAN (bess) | 8 Sep 2023 | 30 Jun 2030 | 75 MW |
| ROTHIENORMAN (bess) | 19 Jan 2026 | 19 Jan 2031 | 50 MW |
Contracted MW as dates arrive
Running total by connection year, years to scale
Table view
| Year | Cumulative MW |
|---|---|
| 2026 | 107 MW |
| 2030 | 182 MW |
| 2031 | 232 MW |
Queue
| Placecalculated by N84 | Project | MW (as published) | MW ahead (N84 order) | Connection date | Gate | Order group | Status (as printed) |
|---|---|---|---|---|---|---|---|
| 1 | ROTHIENORMAN (bess) | 57 MW | 0 MW | 6 May 2026 | not stated | gate not printed | Accepted to Connect |
| 2 | ROTHIENORMAN (bess) | 50 MW | 57 MW | 6 Nov 2026 | not stated | gate not printed | Accepted to Connect |
| 3 | ROTHIENORMAN (bess) | 75 MW | 107 MW | 30 Jun 2030 | not stated | gate not printed | Accepted to Connect |
| 4 | ROTHIENORMAN (bess) | 50 MW | 182 MW | 19 Jan 2031 | not stated | gate not printed | Accepted to Connect |
Receipt: MW and dates as printed in the SSEN Embedded Capacity Register, file dated 1 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order
| Year (MW effective from) | Projects | MW |
|---|---|---|
| 2026 | 2 | 107 MW |
| 2030 | 1 | 75 MW |
| 2031 | 1 | 50 MW |
Projects recorded at this site
| Project (as published) | Technology | MW | Connection date | Status (as printed) |
|---|---|---|---|---|
| ROTHIENORMAN (battery, 75 MW) | Battery storage | 66 MW | 30 Jun 2030 | Accepted to Connect |
| ROTHIENORMAN (battery, 50 MW) | Battery storage | 50 MW | 6 Nov 2026 | Accepted to Connect |
| ROTHIENORMAN (battery, 50 MW) | Battery storage | 50 MW | 19 Jan 2031 | Accepted to Connect |
| ROTHIENORMAN (battery, 57 MW) | Battery storage | 49.9 MW | 6 May 2026 | Accepted to Connect |
| ROTHIENORMAN (onshore wind, 4.3 MW) | Onshore wind | 0 MW | not stated | Connected |
| ROTHIENORMAN (battery, 50 MW) | Battery storage | 0 MW | not stated | Accepted to Connect |
| ROTHIENORMAN (battery, 50 MW) | Battery storage | 0 MW | not stated | Accepted to Connect |
| ROTHIENORMAN (battery, 50 MW) | Battery storage | 0 MW | 27 Feb 2026 | Accepted to Connect |
| ROTHIENORMAN (battery, 50 MW) | Battery storage | 0 MW | not stated | Accepted to Connect |
| ROTHIENORMAN (onshore wind, 4.3 MW) | Onshore wind | 0 MW | not stated | Accepted to Connect |
| ROTHIENORMAN (onshore wind, 15 MW) | Onshore wind | 0 MW | 30 Jun 2030 | Accepted to Connect |
| ROTHIENORMAN (battery, 75.6 MW) | Battery storage | 0 MW | not stated | Accepted to Connect |
Contains data from Scottish and Southern Electricity Networks, licensed under CC BY 4.0.
Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.