SCORRADALE

DNO substation.

Contracted here0.01 GWNot yet connected, as printed
Entries in the queue4entries with a printed MW
Earliest connection date31 Mar 2026Already passed, not yet connected

The queue, in order

Order calculated by N84
First in queue12.9 MW across the first 4 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
SCORRADALE (hydro)3 Nov 202231 Mar 20264.8 MW
SCORRADALE (marine)25 Aug 202525 Aug 20264.8 MW
SCORRADALE (wind on)28 Dec 202230 Apr 20271.5 MW
SCORRADALE (wind on)22 Mar 202131 Dec 20271.8 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW10 MW20 MW2026: 10 MW2027: 13 MW2026202713 MW
0 MW10 MW20 MW2026: 10 MW2027: 13 MW2026202713 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
20269.6 MW
202712.9 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1SCORRADALE (hydro)4.8 MW0 MW31 Mar 2026not statedgate not printedAccepted to Connect
2SCORRADALE (marine)4.8 MW4.8 MW25 Aug 2026not statedgate not printedAccepted to Connect
3SCORRADALE (wind on)1.5 MW9.6 MW30 Apr 2027not statedgate not printedAccepted to Connect
4SCORRADALE (wind on)1.8 MW11.1 MW31 Dec 2027not statedgate not printedAccepted to Connect

Receipt: MW and dates as printed in the SSEN Embedded Capacity Register, file dated 1 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
202629.6 MW
202723.3 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
SCORRADALE (onshore wind, 9.5 MW)Onshore wind9.5 MWnot statedConnected
SCORRADALE (onshore wind, 7.13 MW)Onshore wind7.13 MWnot statedConnected
SCORRADALE (onshore wind, 5.7 MW)Onshore wind5.7 MWnot statedConnected
SCORRADALE (tidal or wave, 4.8 MW)Tidal and wave4.8 MW25 Aug 2026Accepted to Connect
SCORRADALE (hydro, 4.8 MW)Hydro and pumped storage4.8 MW31 Mar 2026Accepted to Connect
SCORRADALE (onshore wind, 2.56 MW)Onshore wind2.57 MWnot statedConnected
SCORRADALE (onshore wind, 2.19 MW)Onshore wind2.19 MWnot statedConnected
SCORRADALE (onshore wind, 1.8 MW)Onshore wind1.8 MW31 Dec 2027Accepted to Connect
SCORRADALE (onshore wind, 1.5 MW)Onshore wind1.5 MW30 Apr 2027Accepted to Connect
SCORRADALE (onshore wind, 0.85 MW)Onshore wind0.86 MWnot statedConnected
SCORRADALE (other, 0.85 MW)Other0.86 MWnot statedConnected
SCORRADALE (onshore wind, 0.47 MW)Onshore wind0.48 MWnot statedConnected
SCORRADALE (onshore wind, 13 MW)Onshore wind0 MWnot statedAccepted to Connect
SCORRADALE (hydro, 4.8 MW)Hydro and pumped storage0 MWnot statedAccepted to Connect
SCORRADALE (onshore wind, 9 MW)Onshore wind0 MWnot statedAccepted to Connect
SCORRADALE (onshore wind, 1.5 MW)Onshore wind0 MWnot statedAccepted to Connect

Contains data from Scottish and Southern Electricity Networks, licensed under CC BY 4.0.