N84 Grid

SHIN GRID

DNO substation.

Contracted here0.21 GWNot yet connected, as printed
Entries in the queue3entries with a printed MW
Earliest connection date30 Jun 2031Date printed in the register

The queue, in order

Order calculated by N84
First in queue212 MW across the first 3 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
SHIN GRID (hybrid)9 Dec 202130 Jun 203194.4 MW
SHIN GRID (wind on)28 Feb 202331 Oct 203240 MW
SHIN GRID (wind on)7 Nov 202331 Oct 203277.6 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW125 MW250 MW2031: 94 MW2032: 212 MW20312032212 MW
0 MW125 MW250 MW2031: 94 MW2032: 212 MW20312032212 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
203194.4 MW
2032212 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1SHIN GRID (hybrid)94.4 MW0 MW30 Jun 2031not statedgate not printedAccepted to Connect
2SHIN GRID (wind on)40 MW94.4 MW31 Oct 2032not statedgate not printedAccepted to Connect
3SHIN GRID (wind on)77.6 MW134.4 MW31 Oct 2032not statedgate not printedAccepted to Connect

Receipt: MW and dates as printed in the SSEN Embedded Capacity Register, file dated 1 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
2031194.4 MW
20322117.6 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
SHIN GRID (onshore wind, 77.6 MW)Onshore wind77.6 MW31 Oct 2032Accepted to Connect
SHIN GRID (hybrid, 94.4 MW)Hybrid50 MW30 Jun 2031Accepted to Connect
SHIN GRID (onshore wind, 40 MW)Onshore wind40 MW31 Oct 2032Accepted to Connect
SHIN GRID (onshore wind, 23.46 MW)Onshore wind23.47 MWnot statedConnected
SHIN GRID (hydro, 8.84 MW)Hydro and pumped storage8.84 MWnot statedConnected
SHIN GRID (hydro, 8.84 MW)Hydro and pumped storage8.84 MWnot statedConnected
SHIN GRID (hydro, 0.47 MW)Hydro and pumped storage0.47 MWnot statedConnected
SHIN GRID (onshore wind, 65 MW)Onshore wind0 MW31 Oct 2020Accepted to Connect
SHIN GRID (onshore wind, 66 MW)Onshore wind0 MWnot statedAccepted to Connect
SHIN GRID (onshore wind, 69 MW)Onshore wind0 MWnot statedAccepted to Connect

Contains data from Scottish and Southern Electricity Networks, licensed under CC BY 4.0.

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.