STAINES

DNO substation.

Contracted here0.10 GWNot yet connected, as printed
Entries in the queue2entries with a printed MW
Earliest connection date30 Dec 2037Date printed in the register

The queue, in order

Order calculated by N84
First in queue100 MW across the first 2 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

  • STAINES (solar)21 Dec 2021 to 30 Dec 2037 (gate not printed)
  • STAINES (bess)31 May 2022 to 31 Dec 2037 (gate not printed)
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
STAINES (solar)21 Dec 202130 Dec 203750 MW
STAINES (bess)31 May 202231 Dec 203750 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW50 MW100 MW2037: 100 MW2037100 MW
0 MW50 MW100 MW2037: 100 MW2037100 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
2037100 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1STAINES (solar)50 MW0 MW30 Dec 2037not statedgate not printedAccepted to Connect
2STAINES (bess)50 MW50 MW31 Dec 2037not statedgate not printedAccepted to Connect

Receipt: MW and dates as printed in the SSEN Embedded Capacity Register, file dated 1 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
20372100 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
STAINES (solar, 50 MW)Solar50 MW30 Dec 2037Accepted to Connect
STAINES (battery, 50 MW)Battery storage50 MW31 Dec 2037Accepted to Connect