N84 Grid

STORNOWAY GRID

DNO substation.

Contracted here0.17 GWNot yet connected, as printed
Entries in the queue7entries with a printed MW
Earliest connection date2 Sep 2027Date printed in the register

The queue, in order

Order calculated by N84
First in queue127.62 MW across the first 6 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
STORNOWAY GRID (wind on)2 Sep 20262 Sep 20273 MW
STORNOWAY GRID (wind on)14 May 202531 Dec 202838.92 MW
STORNOWAY GRID (wind on)9 Jan 201931 Oct 203049.7 MW
STORNOWAY GRID (bess)17 Dec 202131 Oct 203025 MW
STORNOWAY GRID (wind on)13 Feb 201928 Feb 20315 MW
STORNOWAY GRID (wind on)10 Jun 201931 Oct 20336 MW
STORNOWAY GRID (wind on)14 Oct 202431 Oct 203345 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW100 MW200 MW2027: 3 MW2028: 42 MW2030: 117 MW2031: 122 MW2033: 173 MW2027202820292030203120322033173 MW
0 MW100 MW200 MW2027: 3 MW2028: 42 MW2030: 117 MW2031: 122 MW2033: 173 MW2027202920312033173 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
20273 MW
202841.92 MW
2030116.62 MW
2031121.62 MW
2033172.62 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1STORNOWAY GRID (wind on)3 MW0 MW2 Sep 2027not statedgate not printedAccepted to Connect
2STORNOWAY GRID (wind on)38.92 MW3 MW31 Dec 2028not statedgate not printedAccepted to Connect
3STORNOWAY GRID (wind on)49.7 MW41.92 MW31 Oct 2030not statedgate not printedAccepted to Connect
4STORNOWAY GRID (bess)25 MW91.62 MW31 Oct 2030not statedgate not printedAccepted to Connect
5STORNOWAY GRID (wind on)5 MW116.62 MW28 Feb 2031not statedgate not printedAccepted to Connect
6STORNOWAY GRID (wind on)6 MW121.62 MW31 Oct 2033not statedgate not printedAccepted to Connect
7STORNOWAY GRID (wind on)45 MW127.62 MW31 Oct 2033not statedgate not printedAccepted to Connect

Receipt: MW and dates as printed in the SSEN Embedded Capacity Register, file dated 1 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
202713 MW
2028138.92 MW
2030274.7 MW
203115 MW
2033251 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
STORNOWAY GRID (onshore wind, 49.7 MW)Onshore wind49.7 MW31 Oct 2030Accepted to Connect
STORNOWAY GRID (onshore wind, 45 MW)Onshore wind44 MW31 Oct 2033Accepted to Connect
STORNOWAY GRID (onshore wind, 38.92 MW)Onshore wind38.92 MW31 Dec 2028Accepted to Connect
STORNOWAY GRID (battery, 25 MW)Battery storage25 MW31 Oct 2030Accepted to Connect
STORNOWAY GRID (onshore wind, 13.78 MW)Onshore wind13.78 MWnot statedConnected
STORNOWAY GRID (onshore wind, 9.03 MW)Onshore wind9.03 MWnot statedConnected
STORNOWAY GRID (onshore wind, 6 MW)Onshore wind6 MW31 Oct 2033Accepted to Connect
STORNOWAY GRID (onshore wind, 5 MW)Onshore wind5 MW28 Feb 2031Accepted to Connect
STORNOWAY GRID (onshore wind, 3.71 MW)Onshore wind3.71 MWnot statedConnected
STORNOWAY GRID (onshore wind, 2.56 MW)Onshore wind2.57 MWnot statedConnected
STORNOWAY GRID (onshore wind, 3 MW)Onshore wind0.07 MW2 Sep 2027Accepted to Connect
STORNOWAY GRID (other, 4 MW)Other0 MWnot statedAccepted to Connect
STORNOWAY GRID (onshore wind, 4.2 MW)Onshore wind0 MW31 Mar 2027Accepted to Connect
STORNOWAY GRID (onshore wind, 0.5 MW)Onshore wind0 MWnot statedAccepted to Connect
STORNOWAY GRID (onshore wind, 10 MW)Onshore wind0 MWnot statedAccepted to Connect
STORNOWAY GRID (onshore wind, 3 MW)Onshore wind0 MWnot statedAccepted to Connect

Contains data from Scottish and Southern Electricity Networks, licensed under CC BY 4.0.

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.