N84 Grid

TAYNUILT GRID

DNO substation.

Contracted here0.22 GWNot yet connected, as printed
Entries in the queue5entries with a printed MW
Earliest connection date31 Oct 2034Date printed in the register

The queue, in order

Order calculated by N84
First in queue215.97 MW across the first 5 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
TAYNUILT GRID (wind on)27 Jun 202331 Oct 203466 MW
TAYNUILT GRID (wind on)30 Aug 202331 Oct 203449.6 MW
TAYNUILT GRID (wind on)9 Oct 202331 Oct 203450 MW
TAYNUILT GRID (bess)16 Oct 202331 Oct 203550 MW
TAYNUILT GRID (hydro)5 Dec 202431 Oct 20350.37 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW125 MW250 MW2034: 166 MW2035: 216 MW20342035216 MW
0 MW125 MW250 MW2034: 166 MW2035: 216 MW20342035216 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
2034165.6 MW
2035215.97 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1TAYNUILT GRID (wind on)66 MW0 MW31 Oct 2034not statedgate not printedAccepted to Connect
2TAYNUILT GRID (wind on)49.6 MW66 MW31 Oct 2034not statedgate not printedAccepted to Connect
3TAYNUILT GRID (wind on)50 MW115.6 MW31 Oct 2034not statedgate not printedAccepted to Connect
4TAYNUILT GRID (bess)50 MW165.6 MW31 Oct 2035not statedgate not printedAccepted to Connect
5TAYNUILT GRID (hydro)0.37 MW215.6 MW31 Oct 2035not statedgate not printedAccepted to Connect

Receipt: MW and dates as printed in the SSEN Embedded Capacity Register, file dated 1 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
20343165.6 MW
2035250.37 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
TAYNUILT GRID (onshore wind, 66 MW)Onshore wind66 MW31 Oct 2034Accepted to Connect
TAYNUILT GRID (onshore wind, 50 MW)Onshore wind50 MW31 Oct 2034Accepted to Connect
TAYNUILT GRID (battery, 50 MW)Battery storage49.9 MW31 Oct 2035Accepted to Connect
TAYNUILT GRID (onshore wind, 49.6 MW)Onshore wind49.6 MW31 Oct 2034Accepted to Connect
TAYNUILT GRID (hydro, 24.7 MW)Hydro and pumped storage24.7 MWnot statedConnected
TAYNUILT GRID (onshore wind, 7.6 MW)Onshore wind7.6 MWnot statedConnected
TAYNUILT GRID (hydro, 6.46 MW)Hydro and pumped storage6.46 MWnot statedConnected
TAYNUILT GRID (hydro, 4.28 MW)Hydro and pumped storage4.28 MWnot statedConnected
TAYNUILT GRID (hydro, 2.85 MW)Hydro and pumped storage2.85 MWnot statedConnected
TAYNUILT GRID (hydro, 0 MW)Hydro and pumped storage2.48 MW28 Feb 2030Accepted to Connect
TAYNUILT GRID (hydro, 2 MW)Hydro and pumped storage2 MWnot statedConnected
TAYNUILT GRID (hydro, 1.9 MW)Hydro and pumped storage1.9 MWnot statedConnected
TAYNUILT GRID (hydro, 1.9 MW)Hydro and pumped storage1.9 MWnot statedConnected
TAYNUILT GRID (hydro, 1.69 MW)Hydro and pumped storage1.69 MWnot statedConnected
TAYNUILT GRID (onshore wind, 1.14 MW)Onshore wind1.14 MWnot statedConnected
TAYNUILT GRID (other, 1 MW)Other1 MWnot statedConnected
TAYNUILT GRID (hydro, 0.85 MW)Hydro and pumped storage0.86 MWnot statedConnected
TAYNUILT GRID (hydro, 0.75 MW)Hydro and pumped storage0.75 MWnot statedConnected
TAYNUILT GRID (other, 0.57 MW)Other0.57 MWnot statedConnected
TAYNUILT GRID (hydro, 0.47 MW)Hydro and pumped storage0.48 MWnot statedConnected
TAYNUILT GRID (hydro, 0.43 MW)Hydro and pumped storage0.43 MWnot statedConnected
TAYNUILT GRID (hydro, 0.38 MW)Hydro and pumped storage0.38 MWnot statedConnected
TAYNUILT GRID (hydro, 0.37 MW)Hydro and pumped storage0.37 MW31 Oct 2035Accepted to Connect
TAYNUILT GRID (other, 0.24 MW)Other0.24 MWnot statedConnected
TAYNUILT GRID (other, 0.24 MW)Other0.24 MWnot statedConnected
TAYNUILT GRID (other, 0.11 MW)Other0.11 MWnot statedConnected
TAYNUILT GRID (hydro, 0.1 MW)Hydro and pumped storage0.1 MWnot statedConnected
TAYNUILT GRID (other, 0.08 MW)Other0.08 MWnot statedConnected
TAYNUILT GRID (onshore wind, 0.08 MW)Onshore wind0.08 MWnot statedConnected
TAYNUILT GRID (hydro, 0.18 MW)Hydro and pumped storage0 MWnot statedAccepted to Connect
TAYNUILT GRID (other, 49.9 MW)Other0 MWnot statedAccepted to Connect
TAYNUILT GRID (onshore wind, 0.2 MW)Onshore wind0 MWnot statedAccepted to Connect
TAYNUILT GRID (onshore wind, 50 MW)Onshore wind0 MWnot statedAccepted to Connect
TAYNUILT GRID (onshore wind, 0.4 MW)Onshore wind0 MWnot statedAccepted to Connect

Contains data from Scottish and Southern Electricity Networks, licensed under CC BY 4.0.

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.