The queue, in order
Dates in the queue
From the earliest date we hold to the connection date printed, in queue order
- THURSO SOUTH GRID (bess)
31 May 2022 to 30 Jun 2027 (gate not printed) - THURSO SOUTH GRID (wind on)
1 Jul 2021 to 29 May 2028 (gate not printed) - THURSO SOUTH GRID (wind on)
15 Aug 2022 to 29 May 2028 (gate not printed) - THURSO SOUTH GRID (bess)
30 Sep 2022 to 31 Oct 2030 (gate not printed) - THURSO SOUTH GRID (wind on)
18 Oct 2023 to 28 Feb 2031 (gate not printed) - THURSO SOUTH GRID (wind on)
9 May 2024 to 30 Sep 2031 (gate not printed) - THURSO SOUTH GRID (bess)
25 Aug 2023 to 31 Oct 2031 (gate not printed) - THURSO SOUTH GRID (bess)
10 Oct 2023 to 31 Oct 2033 (gate not printed) - THURSO SOUTH GRID (hybrid)
18 Dec 2023 to 31 Oct 2033 (gate not printed) - THURSO SOUTH GRID (bess)
8 Apr 2024 to 31 Oct 2033 (gate not printed)
Table view
| Project | From | Connection date | MW |
|---|---|---|---|
| THURSO SOUTH GRID (bess) | 31 May 2022 | 30 Jun 2027 | 49.9 MW |
| THURSO SOUTH GRID (wind on) | 1 Jul 2021 | 29 May 2028 | 12.2 MW |
| THURSO SOUTH GRID (wind on) | 15 Aug 2022 | 29 May 2028 | 8 MW |
| THURSO SOUTH GRID (bess) | 30 Sep 2022 | 31 Oct 2030 | 52.68 MW |
| THURSO SOUTH GRID (wind on) | 18 Oct 2023 | 28 Feb 2031 | 49.9 MW |
| THURSO SOUTH GRID (wind on) | 9 May 2024 | 30 Sep 2031 | 30 MW |
| THURSO SOUTH GRID (bess) | 25 Aug 2023 | 31 Oct 2031 | 50 MW |
| THURSO SOUTH GRID (bess) | 10 Oct 2023 | 31 Oct 2033 | 34.4 MW |
| THURSO SOUTH GRID (hybrid) | 18 Dec 2023 | 31 Oct 2033 | 18.16 MW |
| THURSO SOUTH GRID (bess) | 8 Apr 2024 | 31 Oct 2033 | 50 MW |
Contracted MW as dates arrive
Running total by connection year, years to scale
Table view
| Year | Cumulative MW |
|---|---|
| 2027 | 49.9 MW |
| 2028 | 70.1 MW |
| 2030 | 122.78 MW |
| 2031 | 252.68 MW |
| 2033 | 355.24 MW |
Queue
| Placecalculated by N84 | Project | MW (as published) | MW ahead (N84 order) | Connection date | Gate | Order group | Status (as printed) |
|---|---|---|---|---|---|---|---|
| 1 | THURSO SOUTH GRID (bess) | 49.9 MW | 0 MW | 30 Jun 2027 | not stated | gate not printed | Accepted to Connect |
| 2 | THURSO SOUTH GRID (wind on) | 12.2 MW | 49.9 MW | 29 May 2028 | not stated | gate not printed | Accepted to Connect |
| 3 | THURSO SOUTH GRID (wind on) | 8 MW | 62.1 MW | 29 May 2028 | not stated | gate not printed | Accepted to Connect |
| 4 | THURSO SOUTH GRID (bess) | 52.68 MW | 70.1 MW | 31 Oct 2030 | not stated | gate not printed | Accepted to Connect |
| 5 | THURSO SOUTH GRID (wind on) | 49.9 MW | 122.78 MW | 28 Feb 2031 | not stated | gate not printed | Accepted to Connect |
| 6 | THURSO SOUTH GRID (wind on) | 30 MW | 172.68 MW | 30 Sep 2031 | not stated | gate not printed | Accepted to Connect |
| 7 | THURSO SOUTH GRID (bess) | 50 MW | 202.68 MW | 31 Oct 2031 | not stated | gate not printed | Accepted to Connect |
| 8 | THURSO SOUTH GRID (bess) | 34.4 MW | 252.68 MW | 31 Oct 2033 | not stated | gate not printed | Accepted to Connect |
| 9 | THURSO SOUTH GRID (hybrid) | 18.16 MW | 287.08 MW | 31 Oct 2033 | not stated | gate not printed | Accepted to Connect |
| 10 | THURSO SOUTH GRID (bess) | 50 MW | 305.24 MW | 31 Oct 2033 | not stated | gate not printed | Accepted to Connect |
Receipt: MW and dates as printed in the SSEN Embedded Capacity Register, file dated 1 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order
| Year (MW effective from) | Projects | MW |
|---|---|---|
| 2027 | 1 | 49.9 MW |
| 2028 | 2 | 20.2 MW |
| 2030 | 1 | 52.68 MW |
| 2031 | 3 | 129.9 MW |
| 2033 | 3 | 102.56 MW |
Projects recorded at this site
| Project (as published) | Technology | MW | Connection date | Status (as printed) |
|---|---|---|---|---|
| THURSO SOUTH GRID (battery, 52.68 MW) | Battery storage | 50 MW | 31 Oct 2030 | Accepted to Connect |
| THURSO SOUTH GRID (battery, 49.9 MW) | Battery storage | 49.9 MW | 30 Jun 2027 | Accepted to Connect |
| THURSO SOUTH GRID (battery, 50 MW) | Battery storage | 49.9 MW | 31 Oct 2033 | Accepted to Connect |
| THURSO SOUTH GRID (battery, 50 MW) | Battery storage | 49.9 MW | 31 Oct 2031 | Accepted to Connect |
| THURSO SOUTH GRID (onshore wind, 49.9 MW) | Onshore wind | 49.9 MW | 28 Feb 2031 | Accepted to Connect |
| THURSO SOUTH GRID (onshore wind, 30 MW) | Onshore wind | 30 MW | 30 Sep 2031 | Accepted to Connect |
| THURSO SOUTH GRID (onshore wind, 28.5 MW) | Onshore wind | 28.5 MW | not stated | Connected |
| THURSO SOUTH GRID (battery, 34.4 MW) | Battery storage | 26.5 MW | 31 Oct 2033 | Accepted to Connect |
| THURSO SOUTH GRID (hybrid, 18.16 MW) | Hybrid | 18 MW | 31 Oct 2033 | Accepted to Connect |
| THURSO SOUTH GRID (tidal or wave, 14.15 MW) | Tidal and wave | 14.16 MW | not stated | Connected |
| THURSO SOUTH GRID (onshore wind, 12.2 MW) | Onshore wind | 12.2 MW | 29 May 2028 | Accepted to Connect |
| THURSO SOUTH GRID (onshore wind, 8.74 MW) | Onshore wind | 8.74 MW | not stated | Connected |
| THURSO SOUTH GRID (onshore wind, 8 MW) | Onshore wind | 8 MW | 29 May 2028 | Accepted to Connect |
| THURSO SOUTH GRID (onshore wind, 4.28 MW) | Onshore wind | 4.28 MW | not stated | Connected |
| THURSO SOUTH GRID (biomass, 3.33 MW) | Biomass and waste | 3.33 MW | not stated | Connected |
| THURSO SOUTH GRID (battery, 55 MW) | Battery storage | 0 MW | 28 Feb 2031 | Accepted to Connect |
| THURSO SOUTH GRID (battery, 52.68 MW) | Battery storage | 0 MW | not stated | Accepted to Connect |
| THURSO SOUTH GRID (solar, 22.38 MW) | Solar | 0 MW | not stated | Accepted to Connect |
| THURSO SOUTH GRID (onshore wind, 17.2 MW) | Onshore wind | 0 MW | not stated | Accepted to Connect |
Contains data from Scottish and Southern Electricity Networks, licensed under CC BY 4.0.
Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.