N84 Grid

VENTNOR

DNO substation.

Contracted here0.05 GWNot yet connected, as printed
Entries in the queue2entries with a printed MW
Earliest connection date1 May 2028Date printed in the register

The queue, in order

Order calculated by N84
First in queue48.34 MW across the first 2 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

  • VENTNOR (marine)20 Sep 2021 to 1 May 2028 (gate not printed)
  • VENTNOR (solar)1 Mar 2022 to 25 Aug 2028 (gate not printed)
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
VENTNOR (marine)20 Sep 20211 May 202819.84 MW
VENTNOR (solar)1 Mar 202225 Aug 202828.5 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW25 MW50 MW2028: 48 MW202848 MW
0 MW25 MW50 MW2028: 48 MW202848 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
202848.34 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1VENTNOR (marine)19.84 MW0 MW1 May 2028not statedgate not printedAccepted to Connect
2VENTNOR (solar)28.5 MW19.84 MW25 Aug 2028not statedgate not printedAccepted to Connect

Receipt: MW and dates as printed in the SSEN Embedded Capacity Register, file dated 1 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
2028248.34 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
VENTNOR (solar, 28.5 MW)Solar28.5 MW25 Aug 2028Accepted to Connect
VENTNOR (tidal or wave, 19.84 MW)Tidal and wave19.84 MW1 May 2028Accepted to Connect

Contains data from Scottish and Southern Electricity Networks, licensed under CC BY 4.0.

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.