WITNEY

DNO substation.

Contracted here0.49 GWNot yet connected, as printed
Entries in the queue7entries with a printed MW
Earliest connection date29 May 2026Already passed, not yet connected

The queue, in order

Order calculated by N84
First in queue330.3 MW across the first 6 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
WITNEY (hybrid)29 May 202529 May 2026100 MW
WITNEY (solar)24 Jul 202430 Sep 202618 MW
WITNEY (solar)2 Jun 202131 Aug 202833 MW
WITNEY (hybrid)13 Oct 202131 Aug 202835 MW
WITNEY (hybrid)15 Apr 20241 Nov 203862.4 MW
WITNEY (hybrid)19 Aug 20241 Nov 203881.9 MW
WITNEY (bess)30 Aug 202430 Nov 2038160 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW250 MW500 MW2026: 118 MW2028: 186 MW2038: 490 MW2026202820302032203420362038490 MW
0 MW250 MW500 MW2026: 118 MW2028: 186 MW2038: 490 MW2026203020342038490 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
2026118 MW
2028186 MW
2038490.3 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1WITNEY (hybrid)100 MW0 MW29 May 2026not statedgate not printedAccepted to Connect
2WITNEY (solar)18 MW100 MW30 Sep 2026not statedgate not printedAccepted to Connect
3WITNEY (solar)33 MW118 MW31 Aug 2028not statedgate not printedAccepted to Connect
4WITNEY (hybrid)35 MW151 MW31 Aug 2028not statedgate not printedAccepted to Connect
5WITNEY (hybrid)62.4 MW186 MW1 Nov 2038not statedgate not printedAccepted to Connect
6WITNEY (hybrid)81.9 MW248.4 MW1 Nov 2038not statedgate not printedAccepted to Connect
7WITNEY (bess)160 MW330.3 MW30 Nov 2038not statedgate not printedAccepted to Connect

Receipt: MW and dates as printed in the SSEN Embedded Capacity Register, file dated 1 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
20262118 MW
2028268 MW
20383304.3 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
WITNEY (battery, 160 MW)Battery storage150 MW30 Nov 2038Accepted to Connect
WITNEY (hybrid, 100 MW)Hybrid52.53 MW29 May 2026Accepted to Connect
WITNEY (hybrid, 81.9 MW)Hybrid40 MW1 Nov 2038Accepted to Connect
WITNEY (hybrid, 35 MW)Hybrid35 MW31 Aug 2028Accepted to Connect
WITNEY (solar, 33 MW)Solar33 MW31 Aug 2028Accepted to Connect
WITNEY (hybrid, 62.4 MW)Hybrid29.9 MW1 Nov 2038Accepted to Connect
WITNEY (solar, 18 MW)Solar18 MW30 Sep 2026Accepted to Connect
WITNEY (solar, 18 MW)Solar0 MWnot statedAccepted to Connect

Contains data from Scottish and Southern Electricity Networks, licensed under CC BY 4.0.