N84 Grid

YARNTON

DNO substation.

Contracted here0.11 GWNot yet connected, as printed
Entries in the queue5entries with a printed MW
Earliest connection date27 Feb 2026Already passed, not yet connected

The queue, in order

Order calculated by N84
First in queue105.07 MW across the first 5 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
YARNTON (solar)18 Oct 201927 Feb 202618 MW
YARNTON (solar)14 Jun 202430 Jun 20266 MW
YARNTON (solar)8 Jun 20266 Aug 20273 MW
YARNTON (other)22 Sep 202330 Oct 202748.07 MW
YARNTON (solar)10 Jun 202531 Dec 203730 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW100 MW200 MW2026: 24 MW2027: 75 MW2037: 105 MW202620282030203220342037105 MW
0 MW100 MW200 MW2026: 24 MW2027: 75 MW2037: 105 MW20262029203220352037105 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
202624 MW
202775.07 MW
2037105.07 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1YARNTON (solar)18 MW0 MW27 Feb 2026not statedgate not printedAccepted to Connect
2YARNTON (solar)6 MW18 MW30 Jun 2026not statedgate not printedAccepted to Connect
3YARNTON (solar)3 MW24 MW6 Aug 2027not statedgate not printedAccepted to Connect
4YARNTON (other)48.07 MW27 MW30 Oct 2027not statedgate not printedAccepted to Connect
5YARNTON (solar)30 MW75.07 MW31 Dec 2037not statedgate not printedAccepted to Connect

Receipt: MW and dates as printed in the SSEN Embedded Capacity Register, file dated 1 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
2026224 MW
2027251.07 MW
2037130 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
YARNTON (other, 48.07 MW)Other49.99 MW30 Oct 2027Accepted to Connect
YARNTON (solar, 21.5 MW)Solar21.5 MWnot statedConnected
YARNTON (solar, 18 MW)Solar18 MW27 Feb 2026Accepted to Connect
YARNTON (solar, 6 MW)Solar6 MW30 Jun 2026Accepted to Connect
YARNTON (solar, 3 MW)Solar3 MW6 Aug 2027Accepted to Connect
YARNTON (other, 1.57 MW)Other0.9 MWnot statedConnected
YARNTON (other, 0.4 MW)Other0.4 MWnot statedConnected
YARNTON (other, 0.21 MW)Other0.21 MWnot statedConnected
YARNTON (other, 0.14 MW)Other0.14 MWnot statedConnected
YARNTON (solar, 30 MW)Solar0.11 MW31 Dec 2037Accepted to Connect
YARNTON (other, 0.08 MW)Other0.08 MWnot statedConnected
YARNTON (solar, 22.5 MW)Solar0 MWnot statedAccepted to Connect
YARNTON (battery, 0 MW)Battery storage0 MW1 Nov 2038Accepted to Connect
YARNTON (solar, 6 MW)Solar0 MWnot statedAccepted to Connect
YARNTON (other, 49.9 MW)Other0 MWnot statedAccepted to Connect

Contains data from Scottish and Southern Electricity Networks, licensed under CC BY 4.0.