1Projects in the shown registers
29.9 MWTotal MW as printed
0 / 0Dates later / earlier, files since 8 Sep 2026
0Removed from the register, files since 8 Sep 2026
Built and queued
Capacity already connected against capacity still waiting
- Built: 0.0 GW (100%)
Table view
| Part | GW |
|---|---|
| Built | 0.0 |
| Queued | 0.0 |
| Technology | Projects | MW |
|---|---|---|
| Battery storage | 1 | 29.9 MW |
| Project (as published) | Technology | MW | Current date | Status (as printed) | Connection site |
|---|---|---|---|---|---|
| Care Erskine BEGA | Battery storage | 29.9 MW | not stated | Built | Erskine 132/33kV |
Counts of what the registers printed. No score and no rank.
Supported by National Energy SO Open Data
Contains data from Scottish and Southern Electricity Networks, licensed under CC BY 4.0.
Supported by NGED Open Data
Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.