2Projects in the shown registers
200 MWTotal MW as printed
0 / 0Dates later / earlier, files since 23 Oct 2025
1Removed from the register, files since 23 Oct 2025

Built and queued

Capacity already connected against capacity still waiting

  • Queued: 0.2 GW (100%)
As printed in the shown registers; built is capacity the registers print as connected.
Table view
Built and queued
PartGW
Built0.0
Queued0.2
MW by technology
TechnologyProjectsMW
Battery storage2200 MW
Projects
Project (as published)TechnologyMWCurrent dateStatus (as printed)Connection site
Myreton BESSBattery storage200 MW31 Oct 2028ScopingTealing 132kV Substation
Tealing BESS (100MW)Battery storage0 MWnot statedScopingTealing 132kV Substation

Counts of what the registers printed. No score and no rank.

Supported by National Energy SO Open Data
Contains data from Scottish and Southern Electricity Networks, licensed under CC BY 4.0.
Supported by NGED Open Data