1Projects in the shown registers
299 MWTotal MW as printed
0 / 0Dates later / earlier, files since 23 Oct 2025
0Removed from the register, files since 23 Oct 2025
Built and queued
Capacity already connected against capacity still waiting
- Queued: 0.3 GW (100%)
Table view
| Part | GW |
|---|---|
| Built | 0.0 |
| Queued | 0.3 |
| Technology | Projects | MW |
|---|---|---|
| Gas | 1 | 299 MW |
| Project (as published) | Technology | MW | Current date | Status (as printed) | Connection site |
|---|---|---|---|---|---|
| Progress Power Station | Gas | 299 MW | 28 Jun 2024 | Under Construction/Commissioning | Yaxley 400kV Substation |
Counts of what the registers printed. No score and no rank.
Supported by National Energy SO Open Data
Contains data from Scottish and Southern Electricity Networks, licensed under CC BY 4.0.
Supported by NGED Open Data
Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.