N84 Grid

ENSO GREEN HOLDINGS J LIMITED

Grouped by published name, unverified. Printed as: ENSO GREEN HOLDINGS J LIMITED.

Sign in to watch this developer
2Projects in the shown registers
87 MWTotal MW as printed
0 / 0Dates later / earlier, files since 23 Oct 2025
0Removed from the register, files since 23 Oct 2025

Built and queued

Capacity already connected against capacity still waiting

  • Queued: 0.1 GW (100%)
As printed in the shown registers; built is capacity the registers print as connected.
Table view
Built and queued
PartGW
Built0.0
Queued0.1
MW by technology
TechnologyProjectsMW
Hybrid157 MW
Battery storage130 MW
Projects
Project (as published)TechnologyMWCurrent dateStatus (as printed)Connection site
Rayleigh 2 TertiaryHybrid57 MW31 Oct 2028ScopingRayleigh Main 400kV Substation
Rayleigh GP3Battery storage30 MW30 Oct 2034ScopingRayleigh Main 400kV Substation

Counts of what the registers printed. No score and no rank.

Supported by National Energy SO Open Data
Contains data from Scottish and Southern Electricity Networks, licensed under CC BY 4.0.
Supported by NGED Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.